ROKO Construction Ltd v Mohammed Mohammed Hamid (Civil Appeal No. 0051 0f 2011)
The full judgment
Read the complete, verbatim text of this judgment.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions — always read the source judgment before relying on it.
Holding
The Court of Appeal held that although the respondent had not formally signed the main building contract, his part performance—depositing contract money and allowing construction to proceed—rendered the contract, including its arbitration clause, binding. The tribunal therefore had jurisdiction. The respondent's challenge to the arbitrator's jurisdiction was not made within 30 days under section 16(6), and his application to set aside the award was filed outside the one-month limit under section 34(3), rendering it time barred and incompetent. The appeal was competent under section 66 of the Civil Procedure Act. The Court quashed the High Court decision and reinstated the arbitral award with costs to the appellant.
Facts
The appellant contractor and respondent entered into a construction contract on 15.07.2005 for a residential house in Kololo, Kampala at an agreed sum of shs.1,100,000,000 excluding VAT. The respondent signed the bill of quantities but disputed having signed the main building agreement, which contained an arbitration clause. The respondent paid part of the contract sum and the appellant commenced work. After repeated payment defaults, the appellant terminated the contract on 16.07.2007 and referred the dispute to arbitration. CADER compulsorily appointed a retired Supreme Court Justice as arbitrator. The arbitrator awarded the appellant shs.584,430,571 for work done plus shs.100,000,000 general damages, with interest. The respondent applied to the High Court to set aside the award, contending no concluded arbitration agreement existed. The High Court set aside the award. The appellant appealed. The matter had earlier been remitted by the Supreme Court owing to an improperly constituted Court of Appeal coram, and was reheard afresh.
Issues
- Whether the building contract containing the arbitration clause was validly executed and binding on the parties despite the absence of formal signature.
- Whether the application to set aside the arbitral award was time barred under the Arbitration and Conciliation Act.
- Whether the respondent waived its right to challenge the tribunal's jurisdiction by failing to apply to court within 30 days under section 16(6).
- Whether the appeal was properly before the Court of Appeal and competent.
Orders
- The decision of the High Court is quashed.
- The Arbitral award in CAD/ARB/No.11 of 2007 delivered on 30/06/2009 is reinstated.
- The appeal succeeds with costs to the appellant in the Court of Appeal, the High Court and before the Arbitrator.
Key headnotes
Legislation cited (9)
- Arbitration and Conciliation Act (Cap.4) s.11(4)(c)
- Arbitration and Conciliation Act (Cap.4) s.16(6)
- Arbitration and Conciliation Act (Cap.4) s.16(7)
- Arbitration and Conciliation Act (Cap.4) s.16(8)
- Arbitration and Conciliation Act (Cap.4) s.34(3)
- Constitution of Uganda Article 134(2)
- Judicature Act s.10
- Judicature Act s.36
- Civil Procedure Act s.66
Cases cited (6)
- Fr. Narsensio Begumisa and Others v Eric Tibebaga (Civil Appeal No. 17 of 2002)
- Brogden v Metropolitan Railway Co (1877) 2 App Cas 666
- Credit Finance Corp. Ltd. (Supra)
- Denis Bireije v Attorney General (Civil Application No. 31 of 2005)
- Makula International Ltd v His Eminence Cardinal Nsubuga and Another [1982] HCB 11
- National Social Security Fund and Another v Alcon International Ltd (Civil Appeal No. 15 of 2009)