Alpa Gama Engineering Enterprises Ltd v Attorney General (Civil Appeal No. 54 of 2014)
The full judgment
Read the complete, verbatim text of this judgment.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions — always read the source judgment before relying on it.
Holding
The Court of Appeal partly allowed the appeal. It rejected the claim for a refund of the VAT penalty, finding the URA audit was general, covered a period preceding the contract, and did not apportion the penalty to the suit contract. On the unpaid contract balance, the Court held that once the parties agreed the revised contract price and full execution, the burden shifted to the respondent to prove full payment; absent such proof, the appellant was entitled to the balance of Ug.shs.224,838,247. The Court also raised the interest rate from 10% to 18% per annum, holding that a commercial dispute should attract a commercial rate.
Facts
On 15 August 2008 the appellant contracted with the Government of Uganda to construct the Ministry of Justice regional offices at Arua for Ug.shs.984,618,278 (VAT inclusive). Payment was to be made against certificates issued by the Project Manager. The appellant later requested and obtained a 15% upward adjustment, raising the contract sum to Ug.shs.1,132,311,019. The works were completed and handed over in September 2009. The appellant claimed an unpaid balance and a refund of a VAT penalty of Ug.shs.72,213,230 it paid to URA following an audit. It sued for the balance, the penalty, general damages, interest and costs. The High Court awarded special damages of Ug.shs.17,674,628, Ug.shs.5,605,617 unpaid VAT, general damages of Ug.shs.10,000,000, interest at 10%, and costs. The appellant appealed against the assessment of the balance, rejection of the VAT penalty refund, and the interest rate.
Issues
- Whether the appellant was entitled to a refund of the VAT penalty of Ug.shs.72,213,230 paid to the Uganda Revenue Authority.
- Whether the trial judge properly assessed the unpaid balance due to the appellant under the revised construction contract.
- Whether the trial judge properly evaluated the evidence on the record.
- Whether the trial judge wrongly awarded interest at 10% per annum instead of a commercial rate.
Orders
- Appeal partially succeeds.
- Judgment and orders of the High Court set aside and substituted.
- Award of special damages of Ug.shs.224,838,247 (VAT inclusive) to the appellant as the unpaid balance due on the revised contract price.
- Interest on the above sum at 18% per annum from date of filing the suit in the High Court till payment in full.
- 2/3 of the costs in the Court of Appeal awarded to the appellant in view of partial success.
- Award of general damages of Ugx 10,000,000 by the High Court (not appealed against) maintained.
- Interest on the general damages at court rate from date of High Court judgment (19.12.2013) till payment in full.
- Costs of the suit in the High Court as awarded to the appellant maintained.
Key headnotes
Legislation cited (2)
- Value Added Tax Act, Cap 349
- Judicature (Court of Appeal) Rules S.I 13-10 r.30(1)
Cases cited (7)
- Pandya v R [1957] EA 336
- Executive Director of National Environmental Management Authority (NEMA) v Solid State Limited (Civil Appeal No. 15 of 2015)
- Byabalema and 2 Others v UTC (1975) Ltd (Civil Appeal No. 10 of 1993)
- Administrator General v Bwanika James and 9 Others (Civil Appeal No. 7 of 2003)
- Crown Beverages Ltd v Sendu Edward (Civil Appeal No. 1 of 2005)
- Crane Bank Ltd v Nipun Narottam Bhatia (Civil Appeal No. 2 of 2014)
- Ecta (U) Ltd v Geraldine Namirimu and Another (Civil Appeal No. 29 of 1994)