M and B Engineers Limited v Uganda National Roads Authority and Another (Civil Appeal No. 316 of 2021)
The full judgment
Read the complete, verbatim text of this judgment.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions — always read the source judgment before relying on it.
Holding
The Court of Appeal dismissed a contractor's appeal against the dismissal of its breach of contract claim arising from a terminated bridge construction contract. The court held that waiver of a contractual right requires an express or implied agreement, and merely permitting continued work and imposing liquidated damages did not extinguish the employer's right to terminate. Time for completion was a condition, not a warranty, and its breach, together with abandonment and substandard work, justified termination and seizure of equipment under the contract. The court declined to fault the trial court for not assessing damages where no entitlement existed. The cross appeal failed for want of proof of the counterclaim and because costs were properly denied. Each party bore its own costs.
Facts
By a 2009 agreement, the Government of Uganda, through the Ministry of Works and Transport, contracted the appellant to construct the Birara Bridge. The contract price was revised upwards and the completion date was extended to 30 July 2010. The appellant failed to complete the works by that date and was penalised in liquidated damages for the delay. Despite the penalty and notices of intention to terminate, the appellant did not complete the works. The Ministry alleged frequent stoppages, abandonment of the site for more than 28 days without the Project Manager's permission, and substandard work, ordering demolition and reconstruction of piers and an abutment, which the appellant did not comply with. By letter dated 30 October 2012 the Ministry terminated the contract and, invoking clause 61 of the General Conditions of Contract, retained possession of the appellant's materials, plant and equipment on site. The appellant sued for breach of contract, unjust enrichment, quantum meruit, wrongful seizure and conversion. The High Court dismissed the suit and partially allowed the second respondent's counterclaim on declarations only. The appellant appealed and the second respondent cross appealed.
Issues
- Whether the Ministry of Works and Transport waived or acquiesced in the agreed completion date by permitting the contractor to continue working after that date.
- Whether the trial court erred in holding that the waiver, if any, was express, conditional and temporary.
- Whether failure to complete works within the agreed time was a fundamental breach (condition) or a mere warranty remediable by liquidated damages.
- Whether the contractor stopped works and abandoned the site for more than 28 days without the Project Manager's permission.
- Whether the seizure of the contractor's materials and equipment under clause 61 of the GCC was lawful.
- Whether the trial court erred in relying on substandard work as a ground supporting termination when not stated in the termination letters.
- Whether the trial court was obliged to assess damages despite dismissing the suit.
- Whether the cross appellant proved its counterclaim for overpayment and liquidated damages and was entitled to costs.
Orders
- Appeal dismissed in its entirety.
- Cross appeal dismissed.
- Each party to bear its own costs of both the appeal and cross appeal.
Key headnotes
Legislation cited (6)
- Judicature Act Cap 13 s.11
- Judicature (Court of Appeal Rules) Directions S.I.13-10 r.30(1)(a)
- Civil Procedure Act Cap 71 s.27
- Evidence Act Cap 6 s.101
- Sale of Goods Act Cap 82 s.15
- Civil Procedure Rules S.I 71-1 Order 6 rr.1 and 7
Cases cited (19)
- Interfreight Forwarders v EADB (Supreme Court Civil Appeal No. 33 of 1992)
- Nazmudin Gulam Hussein Viram v Nicholas Roussos (Supreme Court Civil Appeal No. 1 of 2006)
- J K Patel v Spear Motors (Supreme Court Civil Appeal No. 4 of 1991)
- Departed Asians Property Custodian Board v Issa Bukenya (Supreme Court Civil Appeal No. 26 of 1992)
- Uganda Revenue Authority v Stephen Mabosi (Supreme Court Civil Appeal No. 26 of 1995)
- General Parts (U) Limited v NPART (Supreme Court Civil Appeal No. 9 of 2005)
- Richards vs Oppenheim [1950] 1 ER 420
- National Bank of Kenya Limited vs Pipe Plastic Sakowitz (K) Limited and Another (2002) 2EA 503
- Thrift Homes Ltd vs Kays Investment Limited [2015] eKLR
- Lutaya v Attorney General (Supreme Court Civil Appeal No. 10 of 2002)
- Uganda v George Wilson Simbwa (Criminal Appeal No. 37 of 2005)
- Insurance Corporation of the Channel Islands vs The Royal Hotel Ltd [1998] Lloyds Rep IR 151
- Agri-Industrial Management Agency Ltd v Kayonza Growers Tea Factory Ltd & Anor (High Court Civil Suit No. 819 of 2004)
- Bank of Credit & Commercial International S.A. (in liquidation) vs. Ali (2001) 1 All ER 961
- Mute v Elikana and another [1975] 1 EA 201
- Mpungu & Sons Transporters Ltd v Attorney General and Another (Civil Appeal No. 63 of 1999)
- Kaggwa Michael v Olal Mark and 6 others (High Court Civil Appeal No. 10 of 2017)
- Candiru Alice v Amandua Fenisto and Another (High Court Civil Suit No. 19 of 2014)
- Republic versus The Minister of Agriculture ex parte Njuguna & Others [2006] 1 EA 359 (HCK)