Yonasani B.Kanyomozi v Motor Mart(U) Ltd
The full judgment
Read the complete, verbatim text of this judgment.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions — always read the source judgment before relying on it.
Holding
On appeal from the dismissal of a breach-of-contract suit over unfinished vehicle repairs, the Supreme Court held that where the contract fixed no time for completion, the law imputed a term that the work be done within a reasonable time, and the respondent's failure to repair the vehicle from 1987 to 1990 was unreasonable. The trial judge erred in finding waiver or estoppel: mere forbearance to sue does not amount to waiver, which requires mutual agreement to alter the contract, and no representation founded an estoppel. No notice making time of the essence was required. The appeal was allowed and judgment entered for the appellant with special damages of UGX 14,400,000, interest and costs.
Facts
In 1987 the appellant's Bedford tipper lorry was in a bad state, its engine having collapsed. The respondent, Motor Mart, agreed to repair the vehicle and put it in a roadworthy condition, charging and receiving about Shs 1.6 million, with payment largely completed by 1990. When the vehicle was returned to the appellant in December 1990 it broke down on a road test, showing the repairs were incomplete. Motor Mart took the vehicle back and undertook, through Leyland Daf (U) Ltd, to overhaul the engine at its own expense. Spare parts for the out-of-production vehicle proved difficult to obtain and the overhaul was never carried out. Rather than withdrawing the vehicle, the appellant allowed the respondent further chances to complete the work. Having waited without the repairs being completed, he filed suit for breach of contract in January 1993. The contract contained no stipulation as to the time within which the repairs were to be completed.
Issues
- Whether the appellant, by his conduct in allowing the respondent further chances to complete the repairs, waived the legal rights that had accrued to him under the contract up to 1990.
- Whether the appellant was estopped from suing for breaches committed before 21 September 1992 because he had failed to give notice making time of the essence of the contract.
- Whether the Supreme Court should assess the damages itself or remit the case to the High Court.
Orders
- Appeal allowed.
- Judgment of the High Court set aside.
- Judgment entered for the appellant against the respondent in the sum of UGX 14,400,000 special damages, with interest at 6% per annum from the date of filing suit until payment in full.
- Costs of the appeal and in the High Court awarded to the appellant.
Key headnotes
Legislation cited (1)
- Judicature Act 1967 s.4(2)
Cases cited (4)
- Charles Rickards v Oppenheim (1950) 1 All ER 420
- Bird v Hildage (1947) 2 All ER 7
- Nurdin Bandali v Lombank Ltd (1963) EA 304
- Dawsons Bank Ltd v Japan Cotton Trading Co Ltd (1935) AIR PC 79