Mohammed v Roko Construction Ltd [2017] UGSC 13
The full judgment
Read the complete, verbatim text of this judgment.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions — always read the source judgment before relying on it.
Holding
The Supreme Court, on a second appeal, dismissed four of the five grounds and upheld the Court of Appeal. It held that an arbitration clause existed in the building contract and that, even though the appellant had not signed, the doctrine of part performance cured the want of signature once both parties acted on the agreement. The application to set aside the arbitral award was time-barred: under s.34(3) ACA it had to be filed within one month of receipt, and the inconsistent 90-day rule 7(1) of the Schedule could not prevail over the Act. Although the Court of Appeal wrongly relied on s.66 CPA, the appeal to it was competent under s.38(3) ACA. Appeal dismissed with costs.
Facts
The appellant engaged the respondent to complete construction of a residential house at Plot 43B Windsor Close, Kololo, for UShs.1,100,000,000 excluding VAT. The parties signed the bills of quantities, which incorporated clause 36 (an arbitration clause); the respondent also signed the Articles of Agreement and passed them to the appellant, who never returned a signed copy. The appellant paid part of the contract sum, and the respondent began and did substantial work but was not paid for all of it. After serving notices to suspend and then terminate, the respondent invoked arbitration; CADER appointed Justice Karokora as arbitrator, who heard both parties and delivered an award on 30 June 2009 ordering the appellant to pay Shs.584,430,571 plus interest, general damages of Shs.100,000,000, and taxed costs of Shs.92,507,410. The appellant filed an application to set aside the award on 14 January 2010. The High Court set it aside for want of arbitral jurisdiction; the Court of Appeal (on a re-constituted coram) quashed that and re-instated the award, prompting this appeal.
Issues
- Whether there was a written arbitration agreement/clause governing the parties.
- Whether the agreement's want of signature by the appellant rendered the arbitration clause invalid, or whether the doctrine of part performance cured it.
- Whether the application to set aside the arbitral award was made within the time limited by s.34(3) of the Arbitration and Conciliation Act.
- Whether the respondent's appeal to the Court of Appeal was competent, and under which provision it lay.
Orders
- Appeal dismissed.
- Decision of the Court of Appeal upheld.
- Costs of the appeal awarded to the respondent.
Key headnotes
Legislation cited (15)
- Arbitration and Conciliation Act s.9
- Arbitration and Conciliation Act s.11(4)(c)
- Arbitration and Conciliation Act s.34(1)
- Arbitration and Conciliation Act s.34(3)
- Arbitration and Conciliation Act s.34(4)
- Arbitration and Conciliation Act s.35
- Arbitration and Conciliation Act s.36
- Arbitration and Conciliation Act s.38(3)
- Arbitration and Conciliation Act s.72
- Arbitration Rules, First Schedule, rule 7(1)
- Civil Procedure Act s.66
- Contract Act Cap 73 s.3(1)
- Contract Act Cap 73 s.3(2)(a)
- Contract Act Cap 73 s.3(4)
- Constitution of Uganda Article 134(2)
Cases cited (7)
- Masembe v Sugar Corporation and Another (Civil Appeal No. 1 of 2000)
- Kifamunte Henry v Uganda [1997] LLR 72 (SCU)
- Credit Finance Corporation Ltd v Ali Mwakasanga [1959] EA 79
- Roko Construction Ltd v Kakira Sugar Works Ltd (Arbitration Cause No. 7 of 2007)
- Makula International Ltd v His Eminence Cardinal Nsubuga and Another (Civil Appeal No. 4 of 1981)
- Uganda Lottery Ltd v Attorney General (Miscellaneous Cause No. 627 of 2008)
- Brogden v Metropolitan Railway Co (1877) 2 App Cas 666