Attorney General v Alpha Gama Enginering Enterprises Limited (Civil Appeal 25 of 2021)
The full judgment
Read the complete, verbatim text of this judgment.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions — always read the source judgment before relying on it.
Holding
On a second appeal the Supreme Court held that the Court of Appeal erred in computing special damages by applying the revised contract price in isolation from the evidence. Where the Project Manager, as the employer's agent, breaches the contract by refusing to certify final payment after the contractor has completed and handed over the works, the employer is estopped from insisting that entitlement be proved only by that certificate, and the contractor may recover on a quantum meruit. The correct measure is the proven value of the completed works less sums already paid. The award of UGX 224,838,247 was set aside and substituted with UGX 186,669,001 (VAT inclusive); interest, general damages and costs were affirmed.
Facts
Alpha Gama Engineering Enterprises Ltd contracted with the Government of Uganda (Ministry of Justice and Constitutional Affairs) to construct regional offices in Arua at a contract price of UGX 984,618,278 (VAT inclusive). In April 2009 the Ministry's Contracts Committee revised the price upward by 15% to UGX 1,132,311,019 owing to rising material and fuel costs. The contractor completed the works and handed over the premises in September 2009. The Project Manager issued a final certificate in September 2009 based on the original contract price (UGX 984,653,972) and declined to certify the contractor's revised final account (Exhibit P10), submitted on 5 October 2009, treating it as time-barred. The Ministry paid UGX 907,442,772. The contractor sued to recover the balance. The High Court awarded special damages of UGX 17,674,628, general damages of UGX 10,000,000 and costs. On the respondent's appeal, the Court of Appeal revised special damages upward to UGX 224,838,247 using the revised contract price, with interest and costs. The Attorney General appealed to the Supreme Court against the award of special damages.
Issues
- Whether the Court of Appeal erred in law in awarding the respondent special damages of UGX 224,838,247 (VAT inclusive).
- Whether the Court of Appeal erred in holding that the trial judge wrongly relied on the Project Manager's final certificate in assessing the unpaid balance.
- Whether, in the absence of a final payment certificate, the contractor could prove its entitlement to payment and on what basis.
Orders
- The appeal substantially fails and only partially succeeds, to the extent of correcting an error in computation by the Court of Appeal based on a wrong principle.
- The Court of Appeal's award of UGX 224,838,247 in special damages is set aside and substituted with UGX 186,669,001 (VAT inclusive).
- Interest of 18% per annum on the substituted award from the date of filing the suit till payment in full is upheld.
- Costs of three-quarters in the Supreme Court and two-thirds in the Court of Appeal are awarded to the respondent.
- General damages of UGX 10,000,000 in favour of the respondent are affirmed.
- Interest at court rate on the general damages from the date of the High Court judgment (18 December 2013) till payment in full is affirmed.
- Costs of the High Court proceedings to the respondent are affirmed.
Key headnotes
Legislation cited (4)
- Evidence Act Cap 6 s.101(1)
- Evidence Act Cap 6 s.57
- Civil Procedure Rules Order 6 rule 7
- Rules of the Supreme Court rule 30(1)
Cases cited (13)
- Godfrey Ssebanakita v Fuelex (U) Ltd (Civil Appeal No. 4 of 2016)
- Mpungu & Sons Transporters Ltd v Attorney General (Civil Appeal No. 17 of 2000)
- Peters v Sunday Post Limited [1958] EA 421
- Trustees of Marc Gilbard 2009 Settlement Trust v O.D. Developments & Projects Ltd [2015] EWHC 70 (TCC)
- Uganda Telecom Ltd v Tanzanite Corporation [2005] EA 331
- Fang Min v Belex Tours (Consolidated Civil Appeals No. 6 of 2013 and No. 1 of 2014)
- Kasifa Namusisi v Ntabaazi (Civil Appeal No. 4 of 2005)
- Bhom v Car and General Ltd (Civil Appeal No. 12 of 2002)
- Lombard North Central plc v Butterworth [1987] 1 All ER 267
- Craven-Ellis v Canons Ltd [1936] 2 All ER 1066
- Clarke v Cuckfield Union Guardians
- Lawford v Billericay Rural District Council
- Alpha Gama Engineering Enterprises Ltd v Attorney General (HCT-00-CC-CS 438 of 2010) [2013] UGCommC 213