Aerophoto Systems Engineering Co. Ltd v Fugro Aperio Ltd & Anor (CAD ARB 16 of 2016)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that the Applicant, though designated as a sub-contractor, was part of a joint venture arrangement disclosed in the Technical Bid Submission Sheet and was entitled to invoke the arbitration clause in the main contract. The tribunal found that the contract structure, particularly the designation of the First Respondent as Member in Charge and the exception for named sub-consultants, indicated a joint venture vehicle. The arbitration clause applied generically to the joint venture contractor and specified sub-contractors. The First Respondent could not rely on non-compliance with mutual consultation as an estoppel where it had itself contributed to the lethargy in that process.
Outcome
Single arbitrator to be appointed to hear the dispute between the parties
Facts
The Applicant was named as a sub-consultant in a Technical Bid Submission Sheet submitted by the First Respondent to the Second Respondent for a contract. The First Respondent was designated as Member in Charge of the joint venture. A dispute arose when the First Respondent refused to pay outstanding amounts totaling UGX 588,139,263 and additional expenses of UGX 184,900,000 claimed by the Applicant. The Applicant sought appointment of an arbitrator under the main contract's arbitration clause, which provided for arbitration under Ugandan law. The First Respondent argued that the Applicant was a mere sub-contractor bound by a separate sub-contract containing an arbitration clause designating England and Wales as the seat. The First Respondent also contended that the Applicant had not complied with pre-arbitration mutual consultation requirements.
Issues
- Whether the Applicant, as a sub-contractor named in the Technical Bid Submission Sheet, is entitled to invoke the arbitration clause in the main contract between the First Respondent and Second Respondent.
- Whether the Applicant is bound by the arbitration clause in the sub-contract No.J4104-22606 designating England and Wales as the seat of arbitration.
- Whether the Applicant has complied with the pre-arbitration mutual consultation requirement under the contract.
Orders
- Application granted.
- Applicant entitled to appointment of a single arbitrator pursuant to Section 10(2) of the Arbitration and Conciliation Act.
- Half costs of the application awarded to the Applicant.
- List of arbitrators to be issued in consequential ruling.
Rules and key headnotes
Legislation cited (3)
- Arbitration and Conciliation Act s.3
- Arbitration and Conciliation Act s.10(2)
- Arbitration Act 1996 (England and Wales)
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.