Alpha Gama Engineering Enterprises Led v Attorney General (HCT-00-CC-CS 438 of 2010)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that where payment under a construction contract is based on certificates issued by a Project Manager, the contractor's entitlement is limited to the certified amount, not the estimated contract price. The final certificate, confirmed by the contractor's own commissioning report, determines the sum owed. A contractor disputing the Project Manager's certification must invoke the contractual dispute resolution mechanism within 14 days. The Plaintiff recovered special damages based on the difference between the certified amount and payments received, plus general damages and interest.
Outcome
Plaintiff awarded UGX 33,280,245 comprising unpaid VAT, special damages, and general damages, with interest and costs
Facts
The Government of Uganda contracted the Plaintiff to construct regional offices in Arua at a contract price of UGX 984,618,278. During construction, the Plaintiff sought a 15% upward price adjustment due to rising costs of fuel, timber, cement, steel, sand, and stone. The Solicitor General approved the variation, raising the contract price to UGX 1,132,311,019. The Plaintiff completed construction and the building was commissioned on 15 September 2009. By handover, the Plaintiff had received UGX 754,025,725. The Defendant made a further payment of UGX 110,050,414 on 15 March 2010. The Plaintiff claimed a balance of UGX 340,448,110 including retained VAT and URA penalties. The Defendant contended it had paid all sums due according to the final payment certificate dated 3 March 2009. The Plaintiff's own commissioning report stated the certified total project cost as UGX 930,753,017 including VAT.
Issues
- Whether the Plaintiff was entitled to the sum claimed.
- What remedies were available to the parties.
Orders
- Judgment entered in favour of the Plaintiff.
- Plaintiff awarded UGX 5,605,617 towards VAT.
- Plaintiff awarded UGX 17,674,628 as special damages.
- Plaintiff awarded UGX 10,000,000 as general damages.
- Interest on special damages at 10% per annum from 5 September 2009 until payment in full.
- Interest on general damages at court rate from date of judgment until payment in full.
- Defendant to pay costs of the suit.
Rules and key headnotes
Cases cited (4)
- Hall Brothers SS Company Ltd v Young (1939) 1 KB 748
- Storms v Hutchinson (1905) AC 515
- Bhandeha Habib Ltd v Commissioner General - URA (1997-2001) UCL 202
- Harbutts Plasticine Ltd v Wyne Tank and Pump Co. Ltd (1970) 1 CHD 447
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.