Alpha Gama Engineering Enterprises Ltd v Attorney General (Civil Suit No. 377 of 2009)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The High Court held that a contractor instructed by a Project Manager to execute additional works under a variation clause in a construction contract is entitled to payment, even without formal procurement clearance. The Project Manager had contractual authority to order variations. The contractor has no duty to verify whether internal consent procedures were followed. The State cannot avoid liability by invoking its internal administrative failures. The Plaintiff was awarded outstanding payment for variation works plus interest. Retention fees remain unpaid pending certification of defect correction.
Outcome
Judgment entered for the Plaintiff with awards for outstanding contract payments, interest, general damages, and costs. Retention fee claim dismissed without prejudice pending certification.
Facts
In September 2007, the Plaintiff contracted with the Government of Uganda (Ministry of Internal Affairs) to construct an administrative block at Kabalye Police Training School, Masindi for Uganda shillings 419,220,252/=. Before completion in March 2008, the Project Manager (Force Estates Officer) instructed the Plaintiff to carry out additional works including enlargement of the parking yard, parade ground, and access roads. Written confirmation of these instructions was given on 14 May 2008 and 6 June 2008. The additional works totalled Uganda shillings 154,971,760/=. The building was commissioned by the President in December 2008 and is in use. The Plaintiff was paid Uganda shillings 47,000,000/= after suit was filed but the balance of Uganda shillings 107,675,895/= remained unpaid. The Plaintiff also claimed retention fees of Uganda shillings 24,733,969/= from the original contract. The Attorney General defended on grounds that the Project Manager lacked authority to order additional works without formal procurement approval and Attorney General clearance.
Issues
- Whether the Plaintiff Company was instructed by the Government of Uganda as represented by the Ministry of Internal Affairs to execute extra works worth Uganda shillings 151,187,000 at Kabalye Police Training School, Masindi.
- Whether the Plaintiff was paid by the Government of Uganda represented by the Ministry of Internal Affairs for the additional/extra works for the Administration Block at Kabalye Police Training School, Masindi.
- Whether the Plaintiff is entitled to retention fees of Uganda shillings 24,733,969/=.
Orders
- Plaintiff awarded Uganda shillings 107,675,895/= being the outstanding balance for additional works.
- Retention fee claim of Uganda shillings 24,733,969/= dismissed without prejudice to future claim upon proof of Project Manager certification that defects had been corrected.
- Interest awarded at 25% per annum on the principal sum from January 2009 to the date of judgment.
- General damages for inconvenience awarded in the sum of Uganda shillings 21,000,000/=.
- Further interest at Commercial Bank of Uganda lending rate of 21% per annum from date of judgment to payment in full on decreed sums.
- Costs of the suit awarded to the Plaintiff.
Rules and key headnotes
Legislation cited (10)
- Government Proceedings Act Cap. 77
- Public Procurement and Disposal of Public Assets Act 2003 s.59(2)
- Public Procurement and Disposal of Public Assets Act 2003 s.59(3)
- Public Procurement and Disposal of Public Assets Act 2003 s.3
- Constitution of Uganda 1995 article 119
- Constitution of Uganda 1995 article 119(5)
- Civil Procedure Act s.26
- Civil Procedure Act s.26(2)
- Civil Procedure Rules Order 9 rule 20(1)(a)
- Civil Procedure Rules Order 9 rule 27
Cases cited (4)
- Nsimbe Holdings Limited v Attorney General (Constitutional Petition No. 2 of 2006)
- Kisugu Quarries Limited v Administrator General (Supreme Court Civil Appeal No. 10 of 1998)
- Uganda Telecom Limited v Tanzanite Corporation [2005] 2 EA 331
- ECTA (U) Ltd v Geraldine and Josephine Namukasa (Supreme Court Civil Appeal No. 29 of 1994)
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.