Boschcon Civil & Electrical Construction Co (U) Ltd v Salini Construttori SPA (Civil Suit No. 151 of 2008)
Observed later treatment
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The court held that the defendant wrongfully terminated the subcontracts. The defendant misrepresented its VAT status by indicating the contract sum was plus VAT but later claiming exemption, causing financial strain to the plaintiff. The defendant caused delays through withholding payments, delayed supplies, and unresolved VAT and store supply issues. The termination was unjustified and the plaintiff was awarded UGX 572,287,907 in total damages and interest, with equipment returned. The defendant succeeded partly on counterclaim for materials supplied worth UGX 273,450,449, which was offset against plaintiff's award.
Outcome
Plaintiff's main suit largely succeeded with damages awarded and equipment ordered returned. Defendant's counterclaim partly succeeded for materials supplied. Counterclaim amount to be offset from plaintiff's total award.
Facts
Boschcon was subcontracted by Salini to construct residential camp houses at Bujagali Hydroelectricity Plant under two separate agreements signed in July and October 2007. The letter of intent stated the contract sum was plus VAT, but the final subcontracts were silent on VAT. After commencement, the plaintiff incurred VAT on purchases totaling UGX 100,224,441 but Salini rejected refund claims stating it was VAT exempt under the VAT Amendment Act 2007. Disputes arose over store supplies reconciliation and withheld payments on certificates. Delays occurred and revised programmes were requested. On 16 May 2008, Boschcon declared a dispute and suspended work citing unresolved store supply issues and inability to continue without materials. Salini terminated the contract the next day citing unilateral suspension and delay. Boschcon's officers and equipment were removed from site with armed guards. Salini completed the works using Boschcon's materials left on site.
Issues
- Whether the termination of the contract by the defendant was lawful.
- Whether there was misrepresentation by the defendant regarding VAT obligations.
- Whether there was misrepresentation by the plaintiff regarding its financial status.
- Who caused the delay in completing the contract.
- Whether the plaintiff is entitled to special and general damages.
- Whether the defendant is entitled to the counterclaim for special and general damages.
Orders
- Judgment entered for the plaintiff in the main suit.
- Defendant to pay plaintiff UGX 100,224,441 being unpaid VAT refund.
- Defendant to pay plaintiff UGX 172,063,466 being outstanding payments on certificates.
- Defendant to pay plaintiff UGX 300,000,000 as general damages for unlawful termination.
- Interest at 25% per annum on special damages from date of filing suit till payment in full.
- Interest at 21% per annum on general damages from date of judgment till payment in full.
- Plaintiff awarded 80% of taxed bill of costs.
- Defendant to return plaintiff's construction equipment and machinery immediately.
- Judgment entered for defendant on counterclaim for UGX 273,450,449 being outstanding costs of materials supplied.
- Interest awarded at 21% per annum on counterclaim amount from date of filing till payment in full.
- Counterclaim amount to be offset from plaintiff's award.
Rules and key headnotes
Legislation cited (2)
- VAT (Amendment) Act No. 6 of 2007 s.1
- Civil Procedure Rules Order 6 rule 7
Cases cited (12)
- Cheshire & Fifoot on Law of Contract, Eleventh Edition at page 257
- Harlsbury's Laws of England 4th Edition Vol. 31 at page 461
- Fox v Mackreth (1788) 2 Cox Eq. Cas 320
- Chitty on Contracts Volume I General Principles Paragraph 6-085 at page 378
- Interfreight Forwarders (U) Ltd v East African Development Bank (SCCA No. 33 of 1993)
- Kituni Construction Company Ltd v Julius Okeny (HCT-00-CC-CS-0250-2004)
- Lodder v Slowey [1904] AC 442
- Harburr's Plasticine Ltd v Wyne Tank & Pump Co Ltd [1970] 1 QB 447
- Petrocity Enterprises (U) Ltd v Security Group (U) Ltd (Civil Suit No. 869 of 2004)
- Compania Naviera Maropon SA v Bowaters Lloyd, Pulp and Paper Mills Ltd [1955] 2 QB 68
- African Highland Produce Ltd v Kisorio [2001] EA 1
- Samwiri Masa v Rose Achieng [1979] HCB 29
Cases citing this judgment (2)
How later Ugandan judgments in the Wakilii corpus have cited this case. Treatment labels come from Sequitur — Uganda’s citator — each backed by a verbatim span from the citing judgment, and are not an assertion that this case is, or is not, good law.
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.