British East Africa Corporation Limited v Kanji and Another (Civil Appeal No. 16 of 1939)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that an objection for non-joinder of an essential party must be taken at the earliest opportunity and was therefore overruled on appeal. Held further that under the terms of the contract, where the parties agreed that all disputes should be assessed solely by the architect acting as sole arbiter, his certificate given after proper consideration of both sides was final and binding. A technical submission and formal arbitration reference were not necessary under the contract. The architect's assessment and certificate, having been given after the application of his professional knowledge and due consideration of the disputed matters, constituted a sufficient and conclusive award. Appeal allowed.
Outcome
Appeal allowed. Architect's certificate held to be final and binding under the contract. Cross objection on quantum of goods supplied partly succeeded, reducing defendants' claim by Sh. 4,747.
Facts
Respondents contracted to build three houses in Mombasa for appellants in 1925. The contract followed the Royal Institute of British Architects standard form but cancelled the formal arbitration clause and substituted clause 17, which appointed the architect as sole arbiter to assess and settle all disputes. The architect issued interim certificates which were paid. Respondents then submitted a claim for extras and variations totalling Sh. 53,333. The architect met respondents on site, went through the items, and prepared an assessment substantially cutting down the claim to Sh. 31,786. Respondents rejected this assessment and brought suit in 1927. Appellants paid Sh. 26,936 into court (the amount due on the architect's certificate after deduction for goods supplied) and resisted the balance on the ground that the architect's certificate was final and binding. The lower courts held that the certificate was not conclusive because it was given after a dispute had arisen between the parties and gave judgment substantially for the plaintiffs.
Issues
- Whether a preliminary objection on the ground of non-joinder of an essential party can be raised on appeal when it was not pressed at trial.
- Whether the architect's certificate is final and binding on the parties where clause 17 appoints the architect as sole arbiter to assess and settle all disputes.
- Whether a formal submission, reference, and award are necessary for the architect's decision to constitute a binding arbitral award under the contract.
- Whether the architect properly assessed the disputes relating to extras and variations, including stone work, teak screens, and the schedule of prices.
- Whether the amount to be deducted for goods supplied by the defendants to the contractors was correctly assessed.
Orders
- Appeal allowed.
- Preliminary objection on the ground of non-joinder overruled.
- Cross objection in respect of Sh. 4,747 for goods supplied allowed.
- Plaintiff entitled to interest at 9% on Sh. 26,936/33 from 3 March 1927 to date of payment into court.
- Plaintiff entitled to interest at 9% on Sh. 4,747 from 3 March 1927 to 29 December 1928 and from 21 September 1936 to date of judgment, thereafter at 6% until final adjustment.
- Plaintiff entitled to costs of the suit on Sh. 31,683/33 up to date of payment into court.
- Plaintiff allowed Sh. 500 costs in respect of the Sh. 4,747 underpaid.
- Defendants entitled to three-quarters of their costs of the suit subsequent to date of payment in.
- Defendants entitled to costs of the appeal.
- Plaintiff entitled to costs of the cross objection to the extent of Sh. 4,747.
Rules and key headnotes
Legislation cited (2)
- Civil Procedure Code, 1882 s.34
- Indian Contract Act s.45
Cases cited (11)
- Sheehan v Great Eastern Railway Company (16 Ch. 59)
- Sharpe v San Paulo Railway Co (1873 Ch App 609)
- Laidlaw v Hastings Pier Co (1874)
- Stevenson v Watson (1879) 4 CPD 148
- Lloyd Brothers v. Milward, reported in Hudson on Building Contracts, 2nd Edition, at pages 454
- Clemence v. Clark, reported in Hudson on Building Contracts, 2nd Edition, at page 207
- Richards v May (1883) 10 QBD 400
- Goodyear v Weymouth (35 LJCP 12)
- Rain Sebuk v Ramlall Koondoo (6 Calcutta 815)
- Batterbury v Vyse (2 H & C 42)
- Ludbrook v Barrett (36 LT 616)
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.