BuildTrust Construction (U) Limited v Rugasira (HCT-00-CC-CS 288 of 2005)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
A fixed-price construction contract may be varied by oral instructions where both parties continue performance despite the variations. The common law will impose a quasi-contract requiring payment for renovation work done and accepted outside the strict contractual parameters. Where parties commission an independent expert to value disputed variations, courts will promote reconciliation by enforcing that valuation unless there is good reason not to do so. Delay caused by ordering additional works sets the completion time at large, requiring performance within a reasonable time, not the original contractual deadline.
Outcome
Plaintiff's claim substantially allowed with award of unpaid contract sum and damages. Defendant's counterclaim partly allowed with award for rental loss due to delay and general damages for breach.
Facts
By written contract dated 20 June 2002, the defendant contracted the plaintiff to renovate her residential house at Plot 13 Luthuli Avenue, Bugolobi, Kampala for a fixed price of UGX 115,000,000 over five months. The defendant gave numerous verbal instructions for variations during performance, increasing the scope and cost of work. The plaintiff presented a final bill of UGX 220,696,325, which the defendant rejected as unreasonably high. The defendant commissioned independent valuers M/S Barker, Barton & Lawson (BBL) who valued the work at UGX 198,832,579. The plaintiff accepted this valuation. The plaintiff had been paid UGX 135,500,000, leaving a balance of UGX 63,353,571. The renovation was completed ten months late. The defendant counterclaimed for rental loss and costs of completing allegedly unfinished work. The defendant immediately rented the completed house to Uganda Telecom Limited at USD 2,000 per month.
Issues
- Whether the contract was varied in respect to works to be carried out and if so to what extent?
- Whether the plaintiff is entitled to the reliefs sought?
- Whether the plaintiff (defendant by the counterclaim) is in breach of contract?
- Whether the defendant (plaintiff by the counterclaim) is entitled to the relief sought?
Orders
- Plaintiff awarded UGX 63,353,571 being outstanding contract sum.
- Plaintiff awarded UGX 6,000,000 as general damages for inconvenience.
- Interest at 23% per annum on the outstanding amount from 24 July 2004 until payment in full.
- Interest at 8% per annum on general damages from date of judgment until payment in full.
- Plaintiff awarded costs of the main suit.
- Defendant awarded USD 12,000 (or Uganda Shillings equivalent at prevailing commercial bank exchange rate) for loss of rental income due to delay.
- Defendant awarded UGX 2,000,000 as general damages for delay.
- Interest at 4% per annum on USD 12,000 from 9 March 2003 until payment in full.
- Interest at 8% per annum on general damages from date of judgment until payment in full.
- Defendant awarded costs of the counterclaim.
Rules and key headnotes
Legislation cited (1)
Cases cited (4)
- Mujuni Ruhemba v Shansha Jensen (U) Ltd (Court of Appeal No. 56 of 2000)
- [1943] AC 32
- Muhammed Mohammed Al Hassan v Ibrahim Al Gasim (High Court Civil Suit No. 504 of 2005)
- [1959] EA 1071
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.