Bunyonyi Engineering Work Limited v Kampala Capital City Authority (Civil Suit No. 876 of 2018)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that KCCA breached a road construction contract by failing to pay certified sums within 30 days as required by Clause 43.1, failing to pay interest on late payment, failing to hand over contract sites within 7 days of signing, and failing to compensate the plaintiff for equipment damage caused by failure to sensitize neighboring communities. The plaintiff was entitled to the outstanding balance of UGX 76,705,460, compensation of UGX 178,060,000 for losses, payment of UGX 33,150,000 for additional works under quantum meruit, general damages of UGX 20,000,000, interest at 18% per annum, and costs.
Outcome
Judgment entered for the plaintiff with damages, interest, and costs awarded
Facts
The plaintiff was contracted by KCCA to carry out road works on Kirombe, Bukasa, Nalubaale and Amka roads for four months starting 10 August 2012. The contract was signed on 12 July 2012 with a start date of 19 July 2012. KCCA failed to hand over the contract sites until 13 August 2012, causing the plaintiff to lose UGX 36,000,000 in pre-paid equipment hire and incur a further UGX 36,000,000 to re-hire equipment. When the plaintiff's employees attempted to access the Kirombe road site, they were assaulted and their equipment vandalized by neighboring land occupants whom KCCA had failed to sensitize. The plaintiff issued a payment certificate for UGX 147,180,978 on 18 October 2012. KCCA paid only UGX 70,475,518 on 6 December 2012, beyond the contractual 30-day payment period, and failed to pay interest on the late payment. KCCA also instructed the plaintiff to carry out additional emergency works on 19 December 2012 and 22 January 2013 but failed to pay for them. The defendant did not appear at the hearing and the matter proceeded ex parte.
Issues
- Whether the Defendant breached the suit contract.
- Whether the Plaintiff is entitled to payment for additional works done.
- What remedies are available to the parties.
Orders
- The Defendant breached the suit contract.
- The Plaintiff is entitled to payment for additional works done.
- The Plaintiff is awarded UGX 76,705,460 being the outstanding balance under the first payment certificate.
- The Plaintiff is awarded compensation of UGX 178,060,000 for damage and losses caused by the Defendant's breach.
- The Plaintiff is awarded UGX 33,150,000 for additional works carried out.
- The Plaintiff is awarded general damages of UGX 20,000,000.
- Interest at 18% per annum is awarded on UGX 76,705,460 from the date it was first due until payment in full.
- Interest at 18% per annum is awarded on the retention payment of UGX 17,430,443 from 31 May 2018 until payment.
- Interest on general damages is awarded from the date of judgment until payment in full.
- Costs are awarded to the Plaintiff.
Rules and key headnotes
Legislation cited (1)
- Civil Procedure Act Cap.71 s.27
Cases cited (4)
- Ewadra Emmanuel v Spencon Services Limited (High Court Civil Suit No. 22 of 2015)
- Omega Construction Company Limited v Kampala Capital City Authority (High Court Civil Suit No. 780 of 2015)
- M/s Akkermans Industrial Engineering v Attorney General (Civil Suit No. 333 of 2004)
- Kibimba Rice Ltd v Umar Salim (Supreme Court Civil Appeal No. 17 of 1992)
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.