Central Plumbing Works (Uganda) Ltd and Sung Il Co. Ltd v Uganda Civil Aviation Authority (Miscellaneous Application 179 of 2024)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The High Court held that where parties executed a construction contract containing a valid arbitration clause, disputes arising from a product guarantee issued pursuant to that contract fall within the scope of the arbitration agreement. The guarantee was issued within the contractual framework and concerned works undertaken under the main contract. The court found that the dispute was sufficiently connected with the parties' contractual relationship and fell within the arbitration clause. The civil suit was struck out and the matter referred to arbitration under section 5 of the Arbitration and Conciliation Act.
Outcome
Civil suit struck out and dispute referred to arbitration
Facts
The parties executed a construction contract on 12 August 2013 for an extra water reservoir at Entebbe International Airport. The contract contained an arbitration clause in clause SCC 25.4.1. Pursuant to the contract, the second applicant issued a 50-year guarantee dated 16 October 2013 for the water tanks supplied. The respondent subsequently instituted civil suit claiming the applicants supplied defective water tanks and seeking recovery of UGX 646,704,604 plus damages. The parties had previously participated in arbitration proceedings, but the resulting award was set aside by the High Court on 25 January 2024 on grounds that the arbitral tribunal had not been properly constituted. The applicants then applied for the civil suit to be stayed and referred to arbitration, arguing the dispute fell within the arbitration clause. The respondent opposed, contending the claim was founded on the guarantee which was a separate instrument containing no arbitration clause.
Issues
- Whether High Court Civil Suit No. HCT-00-CV-CS-0057-2023 concerns a dispute falling within the parties' arbitration agreement and should therefore be referred to arbitration under section 5 of the Arbitration and Conciliation Act.
Orders
- Pursuant to section 5 of the Arbitration and Conciliation Act (Cap. 5), the dispute between the parties arising out of, or in connection with, the contract dated 12 August 2013 for the construction of an extra water reservoir at Entebbe International Airport is referred to arbitration.
- High Court Civil Suit No. HCT-00-CV-CS-0057-2023 is hereby struck out.
- The costs of this application shall abide the outcome of the arbitration proceedings.
Rules and key headnotes
Legislation cited (3)
Cases cited (9)
- Ambitious Construction Company Limited v Uganda National Cultural Centre (Miscellaneous Application No. 441 of 2020)
- AC Yafeng Construction Co. Ltd v Living World Assembly and Others (Civil Suit No. 739 of 2021)
- National Bank of Kenya Ltd v Pipeplastic Samkolit (K) Ltd and Another [2001] eKLR
- Smile Communications Uganda Ltd v ATC Uganda Ltd and Another (Arbitration Cause No. 4 of 2022)
- Fiona Trust & Holding Corporation and Others v Privalov and Others [2007] UKHL 40
- Babcon Uganda Limited v Mbale Resort Hotel Limited (Civil Appeal No. 87 of 2011)
- Vantage Mezzanine Fund II Partnership v Simba Properties Investment Company Limited and Another (Civil Miscellaneous Application No. 201 of 2020)
- Roko Construction Limited v Pearl Marina Estates Limited (Miscellaneous Application No. 193 of 2023)
- British American Tobacco Uganda Ltd v Lira Tobacco Stores (Miscellaneous Application No. 924 of 2013)
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.