Coil Ltd v Attorney General (HCCS 581 of 2014)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The High Court held that the plaintiff contractor, not the defendant employer, breached the construction contract by submitting false interim payment claims and failing to obtain required advance payment guarantees. The plaintiff's claim was dismissed. The defendant's counterclaim succeeded for recovery of the balance of advance payment unaccounted for by work actually performed, assessed at UGX 55,808,720.
Outcome
Plaintiff's claim dismissed; counterclaim granted with monetary award and interest
Facts
The plaintiff, Coil Limited, was contracted by the Ministry of Tourism, Trade and Industry to construct a National Artisan premises at Makindye for UGX 13,024,981,048. The plaintiff submitted performance and advance payment bonds and received an advance payment of UGX 200,000,000. The plaintiff claimed the defendant failed to pay the balance of the 20% advance payment totalling UGX 2,404,996,209.6, and that the defendant delayed the project by requiring integration of additional acquired plots. The plaintiff submitted interim payment certificates which were rejected as false or exaggerated. The contract was terminated in December 2011 by the Ministry, citing no substantial activity on site despite the advance payment. The plaintiff sued for breach of contract and damages. The defendant counterclaimed, alleging the plaintiff submitted false claims, failed to perform, and abandoned the site, seeking recovery of UGX 150,000,000 representing advance payment unaccounted for by completed work.
Issues
- Whether the contract between Coil Ltd and Attorney General was breached?
- What remedies are available to the parties?
Orders
- Plaintiff's suit dismissed with costs.
- Judgment entered in favour of the Counterclaimant (Attorney General) against the Plaintiff (Coil Limited).
- Counterclaimant awarded UGX 55,808,720.
- Interest on the decretal sum at 15% per annum from 21 December 2010 until payment in full.
- Plaintiff to pay costs of the suits.
Rules and key headnotes
Cases cited (3)
- Musisi Edward v Bebihuga Hilda [2007] HCB 1
- Kibimba Rice Ltd v Umar Salim (SCCA No. 17 of 1992)
- Harbutt's Plasticine Ltd v Wayne Tank and Pump Co Ltd [1970] QB 447
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.