Construction Engineers & builders v Attorney General [1995] UGSC 18
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
On a road construction contract disrupted by the Liberation war, the Supreme Court held that the appellant did not abandon the works; the contract ultimately foundered on the Government's lack of finance, entitling the appellant to repudiate. The trial Judge's findings on Interim Certificates were varied to add omitted sums and retention money. The Currency Reform Statute 1987 applied only to local debts, not to amounts payable in or measured as Deutschmarks or compensation for loss of plant. Claims for economic dislocation and suspension costs failed. The respondent's counterclaim failed. The appeal was allowed, damages for breach awarded as found by the trial Judge, interest reduced from 30% to 12%, and costs awarded to the appellant.
Outcome
Appeal allowed; High Court judgment varied in the appellant's favour, with damages, costs and reduced interest awarded to the appellant and the respondent's counterclaim rejected
Facts
The appellant company contracted with the Government in September 1977 to build a first-class tarmac road from Pakwach to the Arua Municipality boundary, work to be completed by 1 June 1980. The Liberation war intervened and, on 11 April 1979, the Engineer's Representative permitted the works to be suspended. Indian nationals working on the contract were evacuated to Kenya with part of the plant; the company's site offices were destroyed and equipment damaged. Funding originally provided by two Arab States and later sought from OPEC proved unstable, and re-mobilisation was difficult. In 1982 the Government re-designed the contract to a lower specification, which the appellant agreed to reschedule, but in 1983 and finally 1985 the Government said it could make no further payments for lack of funds. The appellant treated this as a breach or abandonment, claimed its dues including foreign-currency elements and special-risk (war) claims, and sued. The respondent denied liability and counterclaimed 6,000,000/= paid on account, alleging the appellant had abandoned the works.
Issues
- Whether the trial Judge correctly assessed the sums outstanding to the appellant under Interim Certificates Nos. 1–6 (including retention money).
- Whether the Currency Reform Statute 1987 applied to sums expressed in or payable as Deutschmarks under the contract.
- Whether the appellant could claim compensation for devaluation or economic dislocation under the special conditions of the contract.
- Whether the appellant abandoned and thereby breached the contract, or whether the respondent repudiated it through lack of finance.
- Whether the respondent was entitled to counterclaim the sum of 6,000,000/= paid on account and damages for breach.
Orders
- Appeal allowed and the judgment of the High Court varied as prayed in prayers 2(a), (b) and (e) of the memorandum of appeal.
- Appellant awarded the full amount proved as outstanding and due (including retention money) on Interim Certificates 1–6 inclusive, setting aside awards (A)(a)–(e) of the High Court judgment.
- Money payable in foreign currency under the Interim Certificates and by way of compensation for loss of plant and establishment is not subject to the Currency Reform Statute.
- Damages for breach of contract awarded in the terms found by the learned trial Judge.
- No award for economic dislocation or suspension costs (prayers (c) and (d) refused).
- Three quarters of the costs of the appeal awarded to the appellant, with a certificate for two counsel.
- Respondent to pay the costs of the suit and the counterclaim to the appellant in the High Court.
- Interest on the monetary claims reduced from 30% to 12% per annum; interest on costs left at 6%.
Rules and key headnotes
Legislation cited (1)
- Currency Reform Statute 1987
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.