Contact Graphics Ltd v Vivilan Metal Project Ltd (HCT-00-CC-CS 939 of 2004)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The High Court dismissed the application to set aside the arbitral award. The court held that the applicant waived the 30-day time limit by failing to object during arbitration proceedings. No evidence of partiality, material mistakes, or conflict with public policy was established. The arbitrator properly evaluated the evidence, and his findings on contract performance, frustration, and the counterclaim were not manifestly erroneous. An application to set aside an arbitral award is not an appeal; the court's role is supervisory, limited to examining whether errors are apparent on the face of the record.
Outcome
Application to set aside arbitral award dismissed with costs to the respondent
Facts
Contact Graphics Limited (applicant) contracted Vivilan Metal Project Limited (respondent) to fabricate and erect advertising billboards in early 2003 for a total contract price of UGX 64,150,000. UGX 42,100,000 was paid, leaving a balance of UGX 22,050,000 outstanding. The respondent instituted High Court Civil Suit No. 423 of 2004 claiming the balance, general damages for breach of contract, interest and costs. The applicant defended on grounds that the respondent breached the contract, which was frustrated when billboards collapsed after erection and the MTN contract was terminated. The dispute was referred to arbitration pursuant to an arbitration clause in the contract dated 1 April 2003. The arbitrator made his award on 24 July 2006 in favour of the respondent. The applicant then applied to set aside the award.
Issues
- Whether the arbitrator failed to comply with the stipulated time within which he should have completed the award.
- Whether the arbitrator expressed evident partiality in the conduct of the arbitral proceedings.
- Whether the award is in conflict with public policy in Uganda and is bad on the face of it.
- Whether the award bears admitted material mistakes.
- Whether the arbitrator exhibited a lack of consideration for evidence on record and thereby made findings of fact which were not justified by the documents before him.
Orders
- Application dismissed.
- Costs awarded to the Respondent.
Rules and key headnotes
Legislation cited (9)
- Arbitration and Conciliation Act Cap 4 s.34(1)
- Arbitration and Conciliation Act Cap 4 s.34(2)(a)(iv)
- Arbitration and Conciliation Act Cap 4 s.34(2)(a)(v)
- Arbitration and Conciliation Act Cap 4 s.34(2)(b)(ii)
- Arbitration and Conciliation Act Cap 4 s.4
- Arbitration and Conciliation Act Cap 4 s.18
- Arbitration Rules Schedule 1 Rule 13
- Civil Procedure Rules Order 6 rule 24
- Constitution of Uganda Article 126(2)(e)
Cases cited (6)
- Campbell V Irwin (1913) 25 CWN 853: 5CWN 957
- Kilembe Mines Ltd v B. M. Steel Limited (MC 02 of 2005)
- Total (U) Limited v Buramba General Agencies (Arb Cause No. 03 of 1998)
- National Social Security Fund and Another v Alcon and Another (Civil Appeal No. 02 of 2008)
- N. Chellapan V Secy, Kerala Estate Electricity Board (1975) 1 SCC 289 (AIR 1975 SC 230)
- Kanyebwera v Tumwebaze [2005] 2 EA 86
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.