Copcot v Godfrey Sentongo & Anor (HCT-00-CC-CS 118 of 2008)

High Court · [2012] UGCOMMC 56 · 2012 Judgment for Defendant on Counterclaim AI-generated summary ↓ Download Pin to watchlist Add to matter
Jurisdiction
Uganda
Case Type
Counterclaim proceeding to trial after plaintiff withdrew original suit by summary procedure
Decision
Judgment entered for counterclaimant with special damages of UGX 298,213,488, interest at 10% per annum from date of judgment, and costs

Observed later treatment

No later-treatment classification is recorded for this judgment.

Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.

AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.

Holding

Court held that where parties to a cotton production support agreement contributed unequally to a common pool fund, they were required to purchase cotton on a pro rata basis. A ginner purchasing in excess of its proportionate contribution was liable to pay a levy to the lead ginner. The court found the counterclaimant proved its contribution of 79% of the budget and that the counter defendant purchased 57% of production despite contributing only 21%, rendering it liable for a levy calculated on excess bales purchased.

Outcome

Judgment entered for counterclaimant with special damages of UGX 298,213,488, interest at 10% per annum from date of judgment, and costs

Facts

Copcot E.A Ltd and Muddu-Awulira Enterprises Ltd were the only authorized ginners in West Nile Zone for the 2003/4 cotton season. Under a Uganda Cotton Development Organization programme, ginners contributed to a common pool fund to support cotton production. The approved budget was UGX 788,516,000. The parties were to contribute equally and purchase cotton on a pro rata basis according to their actual contributions. Muddu-Awulira (the counterclaimant) contributed UGX 623,182,790 (79% of the budget), including a UGX 600,000,000 loan facility from Stanbic Bank. Copcot contributed only UGX 165,333,210 (21% of the budget). Despite contributing only 21%, Copcot purchased 15,390 bales (57% of production) while Muddu-Awulira purchased 11,500 bales (43% of production). The agreement provided that a ginner purchasing in excess of its proportionate contribution would pay a levy of UGX 55.29 per kilogram of seed cotton to the other party. Copcot refused to pay the levy. Muddu-Awulira counterclaimed for UGX 304,305,344 representing the unpaid levy.

Issues

  1. How much did the counterclaimant contribute to the common pool fund in West Nile in the year 2003/4?
  2. Whether the counter defendant owes the counterclaimant any money under the pro-rata arrangement
  3. What remedies are available?

Orders

  • The plaintiff/counter-defendant shall pay the counterclaimant/defendant a sum of UGX 298,213,488 as special damages.
  • Interest is awarded on the special damages at 10% per annum from the date of judgment until payment in full.
  • Costs are awarded to the counterclaimant/defendant.
  • General damages refused.

Rules and key headnotes

Contract Law — Co-operative agreements — Pro rata arrangements
Where parties to a production support agreement contribute unequally to a common pool fund, they are required to purchase output on a pro rata basis according to their respective contributions, and a party purchasing in excess of its proportionate share is liable to compensate the other party through an agreed levy mechanism.
Civil Procedure — Pleadings — Specific denial required
Under Order 6 rule 8 of the Civil Procedure Rules, it is not sufficient for a defendant to deny generally the grounds alleged by the plaintiff; each party must deal specifically with each allegation of fact which they do not admit, and a failure to specifically deny an allegation amounts to an admission of that fact.
Evidence — Burden of proof — Civil cases
In civil cases, the burden lies on the plaintiff to prove their case on the balance of probabilities, and where no evidence is adduced to challenge the plaintiff's testimony, the court may find that the plaintiff has discharged their burden.
Contract Law — Damages — General damages
The award of general damages is in the discretion of the court, but there must be a justifiable basis for the award. A party claiming general damages must show how they were affected by the breach and cannot rely on vague assertions of commercial disadvantage without supporting evidence.
Contract Law — Interest — Basis for award
The rationale for awarding interest is that the defendant has kept the plaintiff out of their money and has had use of it, and should therefore compensate the plaintiff accordingly. Where there is no evidence that the plaintiff demanded payment and was refused, interest may be awarded only from the date of judgment rather than from the date the obligation arose.

Legislation cited (2)

Cases cited (7)

  • Nsubuga v Kavuma [1978] HCB 307
  • Kyambadde v Mpigi District Administration [1983] HCB 44
  • Benedicto Tejuhikirize v Uganda Electricity Board (Civil Suit No. 51 of 1993)
  • Superior Construction and Engineering Ltd v Notay Engineering Industries Ltd (Civil Suit No. 702 of 1989)
  • Masembe v Sugar Corporation and Another [2002] EA 434
  • Hambutt's Plasticine Limited v Wayne Tank and Pump Company Ltd [1970] 1 QB 447
  • Ruth Aliu and 136 Others v Attorney General (Civil Suit No. 1100 of 1998)

Full judgment

↓ Download PDF

The original judgment as reported. Read the original PDF before relying on any passage.

Copcot v Godfrey Sentongo & Anor (HCT-00-CC-CS 118 of 2008) [2012] UGCommC 56 (1 June 2012)