Damuco Investments Limited v Opportunity Bank (U) Limited (Civil Suit 589 of 2019)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that the Plaintiff breached both construction contracts by failing to complete works within the stipulated timelines as agreed in the Addendum dated 5 June 2018. The Defendant did not breach the contracts. Time was of the essence under the Addendum. The contract for ATM room construction was discharged by lapse of time. The Defendant was entitled to enforce the contractual penalty clause of 1% per day for late completion.
Outcome
Judgment entered for the Defendant/Counter-Claimant. Plaintiff/Counter-Defendant held liable for breach of contract and ordered to pay penalty fees, special damages, interest and costs
Facts
On 7 March 2018, the parties executed two contracts: one for construction of fifteen ATM rooms and one for painting the Defendant's branches. The ATM construction contract was varied by an Addendum dated 5 June 2018, which required completion within fifteen days and advanced UGX 35,000,000 to the Plaintiff. The Plaintiff failed to complete the works within the stipulated timeframe. The Defendant terminated the ATM construction contract on 23 July 2018 after the expiry of the agreed period. The Plaintiff received a total of UGX 63,528,813.91 as advance payment but only completed nine of fifteen ATM rooms to 87% completion. The Defendant engaged new contractors to complete the pending works. The Plaintiff claimed it faced hardships including delayed ATM machine delivery, lack of effective communication, absent construction permits, and increased material costs.
Issues
- Whether the Defendant breached the two construction contracts dated 7th March 2018 for construction of ATM rooms and painting of the Defendant's branches?
- Whether the Plaintiff/Counter defendant is liable on the counterclaim?
- What remedies are available to the parties?
Orders
- The Defendant/Counter-Claimant did not breach the contracts dated 7th March 2018 for the construction of the ATM Rooms and painting of the Defendant's branches.
- The Plaintiff/Counter-Defendant is liable to the Defendant/Counter-Claimant for breach of contract.
- The Plaintiff/Counter-Defendant pays the Defendant/Counter-Claimant a sum of UGX 101,454,432 as a penalty fee.
- The Plaintiff/Counter-Defendant pays the Defendant/Counter-Claimant a sum of UGX 6,209,604 as special damages.
- The Plaintiff/Counter-Defendant pays the Defendant/Counter-Claimant simple interest at rate of 17% per annum on the special damages from the 25th June 2018 until payment in full.
- The Defendant/Counter-Claimant is awarded costs of the suit.
Rules and key headnotes
Legislation cited (6)
Cases cited (11)
- Kabaco (U) Ltd v Turyahikayo Bonny (High Court Civil Suit No. 14 of 2021)
- Meridiana African Airlines (U) Ltd v Avma Spares (EA) Ltd (High Court Civil Suit No. 111 of 2017)
- M and B Engineers Ltd v UNRA and another (Court of Appeal Civil Appeal No. 316 of 2021)
- Charles Richards Ltd. Vs. Oppenheim [1950] ALL E.R 420
- Cavendish Square Holding BY v Talal El Makdessi, and ParkingEye Ltd v Beavis [2015] UKSC 67
- Scandinavian Trading Tanker Co AB Y Flota Petrolera Ecuatoriana (The "Scaptrade") [1983] 2 AC 694
- Dunlop Pneumatic Tyre Co Ltd v New Garage and Motor Co Ltd (Dunlop) [1915] AC 79
- Deluxe Enterprises Ltd v Uganda Leasing Co Ltd (Court of Appeal Civil Appeal No. 13 of 2004)
- Premchandra Shenoi & Anor v Maximov Oleg Petrovich (Supreme Court Civil Appeal No. 9 of 2003)
- Sietco v Noble Builders (U) Ltd (Supreme Court Civil Appeal No. 31 of 1995)
- Uganda Development Bank versus Muganga Construction Co. Ltd. [1981] HCB 35
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.