Dott Services Ltd v Uganda National Roads Authority & Anor (Miscellaneous Cause No. 228 of 2017)
Observed later treatment
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
An application for temporary injunction to restrain award of a road rehabilitation contract to another contractor pending adjudication was dismissed. The court held there was no triable issue because prior High Court proceedings had quashed the appointment of the adjudicator, meaning no adjudication was pending. The applicant's claimed losses were compensable in damages and thus not irreparable. The balance of convenience favoured the respondent road authority as grant of the injunction would indefinitely delay procurement while the incomplete road continued to deteriorate, posing danger to road users.
Outcome
Application for temporary injunction dismissed with costs
Facts
The applicant Dott Services Ltd and the first respondent Uganda National Roads Authority entered into a contract for rehabilitation of the Nakalama-Tirinyi-Mbale Road (102 km) at a contract price of UGX 73,363,489,275. A dispute arose and the applicant referred the matter to adjudication. On 9 May 2017, the first respondent invoked clause 59.4 of the contract and terminated it. The first respondent then offered the contract to another contractor and sought clearance from the Attorney General. The applicant brought this application seeking temporary injunctions to restrain both respondents from entering into or approving a contract with another contractor pending the adjudication proceedings. However, on 26 October 2017, the High Court in Miscellaneous Application No. 162 of 2017 had delivered a ruling quashing the appointment of the adjudicator Mr. Kafuko Ntuuyo.
Issues
- Whether the applicant has a prima facie case with a likelihood of success.
- Whether the applicant might suffer irreparable injury which would not adequately be compensated by an award of damages.
- Whether the balance of convenience is in favour of the applicant or respondents.
Orders
- Application dismissed.
- Costs awarded to the respondents.
Rules and key headnotes
Legislation cited (2)
Cases cited (7)
- E.L.T Kiyimba Kaggwa v Haji Abdu Nasser Katende [1985] HCB 43
- American Cyanamid Co v Ethicon Ltd [1975] 1 All ER 504
- Daniel Mukwaya v Administrator General (HCCS No. 630 of 1993)
- Erisa Rainbow Musoke v Ahamada Kezala [1987] HCB 81
- Uganda National Roads Authority v Center For Arbitration & Dispute Resolution and Dott Services Ltd (Miscellaneous Application No. 162 of 2017)
- Victoria Construction Works Ltd v Uganda National Roads Authority (HMA No. 601 of 2010)
- J. K. Sentongo v Shell (U) Ltd [1995] 111 KLR 1
Cases citing this judgment (1)
How later Ugandan judgments in the Wakilii corpus have cited this case. Treatment labels come from Sequitur — Uganda’s citator — each backed by a verbatim span from the citing judgment, and are not an assertion that this case is, or is not, good law.
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.