Dott Services Ltd v Uganda National Roads Authority (CAD ARB 31 of 2017)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that under the contract's dispute resolution clauses, an adjudicator could be appointed under Clause 25.2 for any contractual dispute without requiring proof of a prior project manager's decision. The respondent's insistence on proof of a project manager's decision under Clause 24.1 usurped the adjudicator's jurisdiction. The tribunal granted the application for appointment of an adjudicator and awarded costs to the applicant.
Outcome
Application for compulsory appointment of adjudicator granted
Facts
Dott Services Ltd entered into a contract with Uganda National Roads Authority on 2 February 2015 for rehabilitation of the Nakalama-Tirinyi-Mbale Road. On 9 May 2017, UNRA terminated the contract for convenience. On 10 May 2017, the applicant requested the President of the Uganda Institute of Professional Engineers to propose three nominations for an adjudicator. On 13 April 2017, UNRA rejected the request, arguing that the applicant had not identified any specific project manager's decision to be adjudicated and that the request was speculative. Following UNRA's refusal to concede to appointment of an adjudicator, the applicant on 10 May 2017 requested appointment of an arbitrator. The applicant then brought this application for compulsory appointment under the Arbitration and Conciliation Act.
Issues
- Whether the respondent was right to maintain that the project manager's decision was a precondition to the adjudication reference.
Orders
- Application granted.
- An adjudicator shall be appointed under Section 11(4)(c) of the Arbitration and Conciliation Act.
- The appointed adjudicator shall be listed in the consequential ruling.
- Costs of the application awarded to the applicant.
Rules and key headnotes
Legislation cited (4)
Cases cited (3)
- B.M. Steels v Kilembe Mines (CAD ARB 10 of 2004)
- Roko Construction v Aya Bakery (U) Ltd [2007] UGCADER 1
- Penta Consulting Ltd v Uganda Telecom Limited [2017] UGCADER 1
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.