Eclipse EDIL Soil JVC Co. Ltd v Kampala City Council (HCT-00-CC-CS 256 of 2005)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that a valid contract existed between the parties for road maintenance works. Where the employer failed to make advance payments as agreed and provided inadequate supervision, the contractor could not be penalised for incomplete performance. The plaintiff substantially performed 70% of the contract and was entitled to payment on the principle of quantum meruit for work actually done, less amounts already paid. General damages were awarded for breach of contract reflecting the employer's failure to properly assess and pay for work completed.
Outcome
Judgment entered for plaintiff with special and general damages awarded on quantum meruit basis
Facts
The plaintiff was awarded a contract by the defendant for periodic maintenance of Kisalosalo Road, Kawempe Division, at a contract price of Shs.24,720,675/-. The contract was signed on 14 April 2003. The plaintiff commenced works but the defendant failed to make any advance payment as required under the contract. In November 2003, the defendant made a single payment of Shs.5,994,383/-, leaving a substantial balance unpaid. The defendant contended that the plaintiff failed to complete the works and that the quality was poor. The plaintiff's evidence showed that the Division Engineer disappeared following a road accident and that a substitute supervisor lacked competence. The defendant's records of work activities were not signed by the contractor and contained suspicious dating errors. The plaintiff submitted that it completed the works but was not paid the balance due.
Issues
- Whether there was a contract between the plaintiff and the defendant.
- Whether the plaintiff performed its part of the contract.
- Whether the plaintiff is entitled to the reliefs sought.
Orders
- Judgment entered for the plaintiff against the defendant.
- Special damages awarded in the sum of Shs.11,060,323/- (4% withholding tax inclusive).
- General damages awarded in the sum of Shs.3,000,000/-.
- Interest on special damages at Court rate from the date of filing till judgment, and thereafter at commercial rate of 25% per annum.
- Interest on general damages at 25% per annum from the date of judgment till payment in full.
- Plaintiff awarded two-thirds of the taxed costs of the suit.
Rules and key headnotes
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.