Gagawala Nurseru Bed v Busingye Properties Ltd (HCT-00-CC-CS 96 of 2011)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The defendant breached a supply contract by failing to pay for delivered seedlings as agreed. Though the principal sum was subsequently paid after criminal proceedings commenced, the plaintiff was entitled to penalty interest and general damages. A contractual penalty clause of 50% on unpaid invoices was reduced from 50% to 5% as the original provision was unconscionable and unclear in its application.
Outcome
Plaintiff awarded penalty interest, general damages, and costs following defendant's breach of contract
Facts
On 4 October 2010, the plaintiff, a community-based organisation, entered into a contract with the defendant company to supply seedlings worth Ushs. 77,460,000/=. Payment terms were: 10% down payment, 40% after delivery, and 50% two months after completion. The plaintiff delivered the seedlings in October 2010. The defendant paid only Ushs. 16,560,000/=, leaving a balance of Ushs. 60,900,000/=. The defendant issued three cheques totalling Ushs. 57,000,000/=, all of which were dishonoured. The plaintiff filed suit on 23 March 2011. Criminal proceedings were instituted against a director of the defendant company. The parties entered into a Memorandum of Understanding dated 23 June 2011 whereby the defendant agreed to pay the outstanding principal sum of Ushs. 60,900,000/=, which was subsequently paid. The remaining issues for trial were general damages, penalty, interest, and costs.
Issues
- Whether there was breach of contract by the defendant
- Whether the plaintiff is entitled to the remedies sought
Orders
- Defendant found to have breached the contract by non-performance.
- Claim for special damages (principal sum of Ushs. 60,900,000/=) overtaken by events as it was paid after criminal proceedings commenced.
- Penalty interest of 5% on the unpaid invoice awarded, amounting to Ushs. 3,045,000/=.
- General damages of Ushs. 3,000,000/= awarded to the plaintiff.
- Interest at 21% per annum on the penalty from the date of filing suit until payment in full.
- Interest at 8% per annum on general damages from the date of judgment until payment in full.
- Costs of the suit awarded to the plaintiff.
Rules and key headnotes
Legislation cited (2)
- Civil Procedure Rules O.17 r.4
- Civil Procedure Act s.26
Cases cited (2)
- Nakana Trading Co Ltd v Coffee Marketing Board (1994) 2 KALR 15
- JB United Civil Engineering and Building Contractors v Lira Municipal Council (HCCS No. 35 of 2007)
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.