Hardware Solutions Ltd v Daiko Construction Co. Ltd (Civil Application No. 258 of 2017)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
An application to set aside an arbitral award must establish one of the strict grounds enumerated in section 34 of the Arbitration and Conciliation Act. Where the applicant merely challenges findings of fact regarding retention monies and costs without demonstrating any statutory ground for setting aside, the court has no basis to interfere with the arbitrator's award. Disagreement with factual findings does not constitute a ground for setting aside under the Act.
Outcome
Application to set aside arbitral award dismissed with costs to the respondent
Facts
Hardware Solutions Ltd applied to set aside an arbitral award made on 4 October 2016 by Eng. Mbabazi Anania in CADER Arbitration Cause No. 21 of 2016. The arbitrator had awarded Daiko Construction Co. Ltd retention monies of UGX 6,108,705 and costs of UGX 11,533,000. Hardware Solutions contested these awards on grounds that: the arbitrator erred in awarding retention monies when Hardware Solutions' works allegedly contained grave defects requiring rectification at a cost exceeding the retention sum; the arbitrator wrongly awarded costs when Hardware Solutions was not entitled to any claims; and the costs were not taxed. Daiko Construction maintained that the arbitrator had properly found Hardware Solutions breached the contract by failing to pay retention monies, that any defects were considered during the arbitrator's site visit, and that Hardware Solutions had not given notice to Daiko to rectify alleged defects before terminating the contract.
Issues
- Whether the arbitral award made on 4th October 2016 by Engineer Anania Mbabazi in CADER Arbitration Cause No. 21 of 2016 should be set aside.
Orders
- Application dismissed.
- Costs awarded to the respondent.
Rules and key headnotes
Legislation cited (4)
Cases cited (1)
- SDV Transami v Agrimag Ltd (Arbitration Cause No. 2 of 2006)
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.