Hoima Municipal Council v Plinth Technical Works Limited (CAD ARB NO. 63 OF 2017; MISCELLANEOUS APPLICATION 972 2018)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The Court set aside the arbitrator's decision finding he lacked jurisdiction. The contract required disputes to first be referred to an adjudicator under Clause 24, with arbitration available only after adjudication within 28 days of the adjudicator's decision. The respondent prematurely filed for arbitration without exhausting or withdrawing from adjudication. The matter was referred back to adjudication with directions for a new adjudicator and strict timelines.
Outcome
Arbitrator's decision on jurisdiction set aside; matter referred back to adjudication
Facts
Hoima Municipal Council and Plinth Technical Works Limited entered into a roads renovation contract dated 13 December 2014 for UGX 10,434,035,711 with one-year duration. Following mutual disengagement, the parties disagreed on the final account. The respondent claimed UGX 3,069,567,455 outstanding; the Project Manager initially assessed UGX 444,602,351, later revised to UGX 948,009,898. The respondent declared a dispute and referred it to Uganda Institution of Professional Engineers for adjudication on 16 August 2017. An adjudicator, Eng. Daka Michael, was appointed and accepted by both parties, but he never presided. On 17 October 2017, before the adjudication concluded, the respondent filed for arbitration. Victor Odongo was appointed arbitrator on 3 April 2018. The applicant raised a preliminary objection on jurisdiction, which the arbitrator dismissed on 9 November 2018. The applicant then sought to set aside that decision.
Issues
- Whether the arbitrator had jurisdiction to hear the dispute when the adjudication process had not been exhausted.
- Whether the respondent prematurely referred the matter to arbitration before finalizing the contractually mandated adjudication process.
Orders
- Application granted.
- Decision of the Arbitrator dated 9 November 2018 set aside.
- Arbitrator found to have exceeded jurisdiction and exercised powers reserved for the adjudicator.
- Matter referred back to adjudication.
- Preferably a new adjudicator be appointed with strict timelines.
- Each party to bear its own costs for this application.
Rules and key headnotes
Legislation cited (6)
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.