Hotel Greton Ltd v Em Enterprises Africa Ltd (Civil Suit 143 of 2015)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that the plaintiff breached the sub-contracts by failing to formalize a contract with the Ministry of Defense before delivery of goods. The defendant's termination of the sub-contracts was wrongful because the contracts provided only for specific performance as a remedy. No evidence supported the plaintiff's allegation that the defendant sabotaged the contract process. The court declined damages to both parties and directed the defendant to enforce specific performance by requiring the plaintiff to secure the Ministry contract so payment could flow to both parties.
Outcome
Declaration granted in favor of plaintiff that termination was wrongful; damages declined to both parties; defendant directed to pursue specific performance remedy against plaintiff
Facts
Hotel Greton Ltd and EM Enterprises Africa Ltd entered two sub-contract agreements on 19 March 2014 for supply of 3,000 blankets and 4,000 T-shirts to the Ministry of Defense. The sub-contracts required the plaintiff to formalize a contract with the Ministry before the defendant would supply. The defendant procured goods from Turkey and delivered them to Magamaga Barracks in June 2014. At delivery, the defendant discovered the plaintiff had not formalized the Ministry contract. The UPDF received the goods for safe custody and later used them. The plaintiff never secured the formal Ministry contract. The defendant terminated the sub-contracts and sought recovery of its goods or payment. Both parties disputed who delivered the goods and when. The plaintiff sued for unlawful termination; the defendant counterclaimed for payment of expenses and profit.
Issues
- Whether there was a breach of contract and if so by whom?
- Whether the defendant sabotaged the contract process between the plaintiff and Ministry of Defense?
- Whether the defendant wrongfully/unlawfully terminated the sub-contracts made on 19th March 2014?
- Whether the defendant is entitled to the remedies in the counterclaim?
- What remedies are available to the parties?
Orders
- Declaration that the defendant wrongfully and unlawfully terminated the sub-contracts made on 19th March 2014.
- Plaintiff's prayer for general damages of UGX 200,000,000 declined.
- Plaintiff's prayer for interest at 25% per annum declined.
- Defendant's counterclaim for payment of UGX 246,687,500 declined.
- Defendant's counterclaim for refund of goods declined.
- Defendant's counterclaim for general damages declined.
- Defendant's counterclaim for interest at 30% declined.
- Court directs that the defendant enforce its right to specific performance of the sub-contracts by the plaintiff.
- Each party to bear its own costs of the suit.
Rules and key headnotes
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.