Inyatsi Construction Limited v Absa Bank Uganda Limited and Another (Miscellaneous Application No. 1257 of 2024)
Observed later treatment
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that a temporary injunction to restrain a bank from honouring demand guarantees will not be granted absent a clear plea of fraud. Performance guarantees are payable on demand with no questions asked, and the applicant did not establish fraud. The court found no prima facie case, no irreparable injury that could not be compensated in damages, and the balance of convenience favoured the respondents, particularly the government's need to complete a public infrastructure project.
Outcome
Application for temporary injunction dismissed with costs to follow the outcome of the main suit
Facts
On 23 November 2022, the applicant contractor entered into a contract with the Ministry of Water and Environment for construction of Kabuyanda Earth Dam at UGX 84,574,952,685. The applicant received an advance of UGX 14 billion and the 1st Respondent bank issued four demand guarantees (two performance guarantees and two advance payment guarantees) totaling approximately UGX 14.7 billion in favour of the Ministry. The applicant commenced works in August 2023 but achieved only 20% physical progress. The applicant subsequently terminated the contract. On 2 December 2024, the Ministry demanded payment under the guarantees. The applicant filed this application seeking a temporary injunction to restrain the bank from honouring the demands, arguing that termination was at its own initiation and that parties were before an adjudication board to determine validity of termination.
Issues
- Whether the Applicant has satisfied the requirements for grant of an order for temporary injunction.
- Whether the Applicant has established a prima facie case against the Respondents.
- Whether the Applicant will suffer irreparable damage which could not be adequately compensated by an award of damages.
- Whether the balance of convenience is in favour of the Applicant.
Orders
- Application for temporary injunction dismissed.
- Costs of this application to abide the outcome of the main cause.
Rules and key headnotes
Legislation cited (4)
Cases cited (14)
- Kiyimba Kaggwa v Katende [1985] HCB 43
- Kagumoha Kakuyo v Shilla Ninsiima (HCMA No. 13 of 2020)
- BS Mount Sophia PTE LTD VS Join-Aim Pte [2012] SGCA 28
- Uganda Electricity Transmission Co. Ltd v Citibank Uganda Limited & 2 Others (HCMA No. 1397 of 2022)
- Busuulwa Vs National Social Security Fund and Anor
- R Vs Secretary of State for Transport ex parte Factortame Ltd [1991] 1 AC 603
- Giella Vs Cassman Brown & Co. Ltd [1973] EA 358
- American Cyanamid Co. v Ethicon Ltd [1975] 1 All ER 504
- American Cyanamid v Ethicon [1975] AC 396
- Godfrey Sekitoleko and four others v. Seezi Peter Mutabazi and two others
- Edward Owen Engineering Ltd v. Barclays Bank International Ltd and another [1978] 1 QB 159; [1978] 1 Lloyd's Rep 166; and [1978] 1 All ER 976
- Tonny Wasswa v Joseph Kakooza [1989] HCB 79
- Kiyimba Kaggwa v Katende [1985] HCB 43
- American Cyanamid Co. v Ethicon Ltd [1975] 1 All ER 504
Cases citing this judgment (1)
How later Ugandan judgments in the Wakilii corpus have cited this case. Treatment labels come from Sequitur — Uganda’s citator — each backed by a verbatim span from the citing judgment, and are not an assertion that this case is, or is not, good law.
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.