Kaddu v Maruben Corporation (Civil Suit No. 108 of 1993)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The court held that the defendant rightfully terminated the subcontracts without notice under an agreed variation to the contract terms, as the plaintiff's performance was unsatisfactory due to inadequate work force. However, the plaintiff was entitled to payment on quantum meruit for work actually performed because the defendant failed to measure the work in accordance with the contractual procedure requiring notice to the plaintiff. The plaintiff could not claim for the full estimated contract value as it did not complete the work.
Outcome
Plaintiff awarded payment on quantum meruit basis for work actually done; claim for full contract value dismissed
Facts
The plaintiff, a local limited liability company, subcontracted with the defendant, a Japanese corporation, for two jobs: cable laying (estimated at US$ 58,629.84) and conduit pipe laying (estimated at US$ 28,649.75). The plaintiff agreed to complete the work within a schedule. The defendant was to supply materials. The plaintiff commenced both contracts but did not complete either. The defendant complained of slow progress and inadequate workforce. The plaintiff had approximately 20 labourers instead of the agreed 200. Letters of intent provided that the defendant could terminate without notice if not satisfied with performance. The defendant subsequently entered the sites and completed the work itself. The plaintiff claimed unpaid sums of US$ 55,598.43 for work done. The defendant counterclaimed, asserting the plaintiff breached by abandoning the sites and had been fully paid.
Issues
- Whether there was a breach of contract between the parties and if so by which party.
- Whether the plaintiff was properly remunerated as per the terms of the contract.
- What remedy the innocent party is entitled to for breach.
Orders
- The defendant to pay the plaintiff according to the plaintiff's measurement of work done in Contract No. 2, being the difference between US$ 17,861 and the amount already paid.
- Each party to bear its own costs.
Rules and key headnotes
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.