Kampala Capital City Authority v Nalongo Estates Ltd (Miscellaneous Cause No. 31 of 2013)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The High Court dismissed the application to set aside the arbitral award. The court held that an application to set aside an award is not an appeal and the court cannot re-examine evidence considered by the arbitrator. The applicant failed to demonstrate that the arbitrator acted arbitrarily, capriciously, irrationally or exceeded jurisdiction under section 34 of the Arbitration and Conciliation Act. The court found no inconsistencies making the award vague or ambiguous and no grounds for remission were established.
Outcome
Application to set aside arbitral award dismissed
Facts
Kampala Capital City Authority (KCCA) and Nalongo Estates Ltd entered into a management agreement dated 16 May 2006 (later revised 4 December 2008) for Nalongo to manage, develop, control and maintain Centenary Park. KCCA alleged numerous violations including the respondent erecting structures without approved plans, commencing works without prior approval, obstructing the park and failing to maintain it as green open space with unlimited public access. KCCA's predecessor KCC terminated the agreement on 26 April 2012. The matter was referred to arbitration. The arbitrator found in favour of Nalongo Estates on certain issues, declaring the management agreement still subsisting, granting an injunction restraining KCCA from taking over the park, and awarding compensatory damages of UGX 732,553,055 for demolition of structures damaged by KCCA's acts. KCCA applied to the High Court to set aside the award.
Issues
- Whether the arbitral award should be set aside on the ground that the arbitrator did not decide according to considerations of natural justice and fairness.
- Whether the arbitral award is in accordance with the terms of the management agreement between the parties.
- Whether the arbitral award is vague, ambiguous and contradictory thereby making it unjust and incapable of implementation.
- Whether the award contains errors in law and fact on the face of the record.
- Whether the award of compensatory damages for structures erected in breach of contract was irrational and unconscionable.
- Whether the arbitrator exceeded jurisdiction by deciding that the management contract was still subsisting despite alleged breaches.
Orders
- Application dismissed with costs to the respondent.
Rules and key headnotes
Legislation cited (14)
- Arbitration and Conciliation Act cap 4 s.21
- Arbitration and Conciliation Act cap 4 s.28
- Arbitration and Conciliation Act cap 4 s.28(4)
- Arbitration and Conciliation Act cap 4 s.28(5)
- Arbitration and Conciliation Act cap 4 s.34
- Arbitration and Conciliation Act cap 4 s.38
- Judicature Act cap 13 s.14
- Judicature Act cap 13 s.33
- Civil Procedure Act s.98
- Civil Procedure Rules Order 51 rule 1
- Public Procurement and Disposal of Public Assets Regulations reg.263(1)
- Public Procurement and Disposal of Public Assets Regulations reg.263(2)
- Public Procurement and Disposal of Public Assets Regulations reg.263(3)
- Kampala Capital City Act s.19
Cases cited (6)
- Associated Engineering Co. v Government of Andra Pradesh (1991) 4 SCC 93
- Kilemebe Mines Ltd v BM Steel Ltd (High Court Miscellaneous Application No. 002 of 2005)
- Seyani Bros v Cassia Ltd (High Court Civil Appeal No. 128 of 2011)
- SDR Transami v Agrimag Ltd (Arbitration Cause No. 2 of 2006)
- V.G George V India Rare Earths Ltd AIR 199 SC 1409
- NSSF v Alcon (High Court Arbitration Cause No. 4 of 2001)
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.