Kampala Capital City Authority v Zimwe Enterprises, Hardware and Construction Ltd (HCT-00-CC-MA 494 of 2012)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Application to set aside arbitral award dismissed. Court held that where a contractor achieves substantial performance (89% completion) and is wrongfully prevented from completing works by the employer's premature termination, the arbitrator acts within jurisdiction in awarding payment under the doctrine of substantial performance and releasing retention money. The arbitrator properly applied section 28 of the Arbitration and Conciliation Act in deciding according to contract terms and trade usages. Court will not intervene where arbitrator has applied his mind to evidence and contract terms unless manifest partiality or departure from contract is proved. No grounds under section 34 of the Arbitration Act established for setting aside the award.
Outcome
Arbitral award upheld and application to set it aside dismissed with costs to the respondent
Facts
The applicant (Kampala Capital City Authority) engaged the respondent (Zimwe Enterprises) under an admeasurement construction contract. The respondent completed 89% of the contract works valued at UGX 5,526,423,650 out of the total contract sum of UGX 6,218,180,150. The applicant deducted full retention money corresponding to the 89% completion but refused to issue a completion certificate. The Executive Director of KCCA terminated the contract before completion. Additional works beyond the original scope were instructed by the project manager including full road base construction, side drains, and culverts. Extension of time was sought by the respondent due to delayed bitumen delivery (hijacked by Somali pirates), delayed works orders, increased scope, and weather. The matter proceeded to arbitration before Canon Engineer Jonathan Grant Mwedde. The arbitrator awarded the respondent half of the balance of the contract sum (UGX 345,978,250), accumulated retention money, and payment for additional works (UGX 384,997,687) but disallowed liquidated damages claim of UGX 310,909,008. KCCA applied to set aside the award.
Issues
- Whether the arbitral award was issued in accordance with the terms of the contract between the parties.
- Whether the arbitrator misconducted himself in disregarding the terms of the contract.
- Whether the arbitral award bears errors on its face.
- Whether the arbitrator properly applied the doctrine of substantial performance in awarding half of the balance of the contract sum.
- Whether the award of accumulated retention money was justified in circumstances where the contract was terminated before completion.
- Whether the award for additional/extra works was proper where no certification by the project manager was made.
- Whether the arbitral award was intended to unjustly enrich the respondent contrary to public policy.
Orders
- Application dismissed.
- Costs awarded to the respondent.
- Certificate for two counsel declined.
Rules and key headnotes
Legislation cited (8)
- Arbitration and Conciliation Act Cap 4 s.34(1)
- Arbitration and Conciliation Act Cap 4 s.34(2)(9)(vi)(vii)(b)(ii)
- Arbitration and Conciliation Act Cap 4 s.34(2)(3)
- Arbitration and Conciliation Act Cap 4 s.28
- Arbitration and Conciliation Act Cap 4 s.28(5)
- Arbitration and Conciliation Act Cap 4 s.9
- Arbitration Rules r.13
- Evidence Act Cap 6 s.114
Cases cited (6)
- Denis Semakula v Masaka Diocese & 2 Others (1998) 11 KALR 128
- Associated Engineers Co v Government of Andhra Pradesh (1994) SCC 93
- Simbamanyo Estates Ltd v Seyani Brothers Company (U) Ltd (HC Misc Application No. 555 of 2002)
- Mbale Resort Hotel Ltd v Babcom Uganda Ltd (HC MA No. 256 of 2010)
- Rashid Moledina Co v Hoima Ginners Ltd (1967) EA 645
- Kilembe Mines Ltd v BM Steel Ltd (HC Misc Application No. 002 of 2005)
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.