Kencom (U) Ltd v Otada Construction Co. Ltd (Civil Suit No. 60 of 2009)
Observed later treatment
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that the Plaintiff breached the subcontract by failing to complete the road construction within three months as stipulated, causing delays that attracted liquidated damages under the main contract. However, the Defendant also breached by failing to pay the Plaintiff for works certified under interim certificate No. 2. The Plaintiff was awarded UGX 82,176,027 for certified works but was liable for damages caused by delays. The Defendant was awarded damages and recovery of advanced payments. Each party bore its own costs.
Outcome
Plaintiff awarded payment for certified works but held liable for breach through delays. Defendant awarded damages and recovery of advanced payments. Neither party fully succeeded.
Facts
In April 2008, the Defendant subcontracted the Plaintiff to construct 73 km of the Ikumba-Ruhija-Hamayanja road for UGX 390,000,000, with payment at 66% of interim certificates issued by the Ministry of Works and Transport. The Plaintiff commenced works in June 2008 but faced delays due to adverse weather, landslides, bridge damage, and alleged equipment and fuel supply failures by the Defendant. The Defendant paid UGX 109,700,000 under interim certificate No. 1. By September 2008, the contract period expired with only 27% completion. The Ministry of Works rejected extension requests and levied liquidated damages from October 2008. Interim certificate No. 2 for UGX 124,509,132 was issued in January 2009. The Plaintiff demanded payment but the Defendant refused, claiming the Plaintiff had breached by delays and that the Defendant had completed the works under certificate No. 2. The Plaintiff withdrew its equipment in February 2009.
Issues
- Whether the Plaintiff was in breach of the subcontract made by the parties on 15 April 2008.
- Whether the Defendant was in breach of the subcontract made on 15 April 2008.
- Whether the Plaintiff is entitled to payment for the work done.
- Whether the parties are entitled to the remedies sought.
Orders
- Plaintiff awarded UGX 82,176,027 as special damages for works certified under interim certificate No. 2.
- Plaintiff held liable for breach of contract by delays, not entitled to general damages.
- Defendant awarded UGX 9,629,877 for monies advanced beyond plaintiff's entitlement under the first interim certificate.
- Defendant awarded general damages totalling UGX 25,637,148, comprising UGX 6,000,000 liquidated damages levied by the Employer and 10% of UGX 196,371,484.
- Amounts awarded to carry interest at 21% per annum from date of filing suit to date of judgment.
- Decreed sums to carry interest at 14% per annum from date of judgment till payment in full.
- Each party to bear its own costs.
Rules and key headnotes
Legislation cited (3)
Cases cited (5)
- Afro Print Ltd v New Vision Printing and Publishing Corporation (High Court Civil Suit No. 513 of 1996)
- Reigate vs. Union Manufacturing Company (Ramsbottom) Ltd [1918] 1 KB 592
- Shirlaw vs. Southern Foundries [1934] 2 KB 206 at 227
- Trollope and Colis Ltd vs. North West Metropolitan Regional Hospitals Board [1973] 2 ALL ER 268
- Sumter vs. Hedges (1898) 1 QB 673, CA, also cited in Max and Young, 'Cases And Material In Contract Law' at page 459
Cases citing this judgment (2)
How later Ugandan judgments in the Wakilii corpus have cited this case. Treatment labels come from Sequitur — Uganda’s citator — each backed by a verbatim span from the citing judgment, and are not an assertion that this case is, or is not, good law.
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.