Kituni Construction Co. Ltd v Julius Okeny (HCT-00-CC-CS 250 of 2004)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The court held that the defendant breached a lump sum construction contract by ordering the contractor off the site when work had substantially been completed. Under the doctrine of substantial performance, the plaintiff contractor was entitled to recover the full contract price where the defendant failed to provide a consultant to supervise the works, accepted the work as it progressed, and subsequently used the completed building without payment. Oral evidence of contract variation was admissible where no written variation requirement existed in the contract, and the defendant was estopped from denying agreed variations where he monitored and accepted the work as it progressed to near completion.
Outcome
Plaintiff awarded full contract price of Shs.102,528,500 with interest at 20% per annum from date of filing suit until payment in full, plus taxed costs
Facts
On 28 March 2003, the plaintiff construction company entered into a written contract with the defendant to construct a petrol station in Soroti at Plot 143-145 Gweri Road for Shs.102,528,500. The contract was to be completed by 10 July 2003. Upon reaching the site, the plaintiff found the ground soggy, requiring more hardcore and murram than anticipated. The parties orally agreed to use bricks instead of blocks and timber trusses instead of steel trusses to stay within budget. The defendant was to provide a consultant to supervise the works but failed to do so, instead personally monitoring progress. By June 2003, when work had progressed to roofing level, the defendant ordered the plaintiff off the site without notice or payment. The defendant issued post-dated cheques covering the contract price, which were dishonoured. The defendant subsequently used the petrol station from December 2003 without paying for it. The plaintiff sued for the contract price.
Issues
- Whether the agreement was breached and by whom?
- Whether the plaintiff is entitled to the whole contract price or at all?
- What remedies are available?
Orders
- Judgment entered for the plaintiff against the defendant for Shs.102,528,500 as special damages.
- Interest on the special damages at 20% per annum from the date of filing the suit until payment in full.
- Costs of the suit to be taxed and paid by the defendant to the plaintiff.
Rules and key headnotes
Legislation cited (3)
Cases cited (4)
- Hoening v Isaacs [1952] 2 All ER 176
- Bolton v Mahadeva [1972] 1 WLR 1009
- Denis Senkungu v Masaka Diocese & 2 Others [1998] 111 KALR 128
- Dakin H & Co Ltd v Lee [1916] 1 KB 166
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.