Kwalnet Technology Ltd v Plessy Uganda Ltd (Civil Suit No. 634 of 2013)
Observed later treatment
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The High Court dismissed the plaintiff's claim for outstanding contract price on the basis that the plaintiff completed only 45% of contracted works, not the 81.56% alleged, and failed to prove substantial performance. The plaintiff breached the contract by failing to complete the works by the agreed deadline. The doctrine of substantial performance requires completion of all but minor omissions; a 55% shortfall is not minor. Where a contract requires completion before payment and completion does not occur by the contractor's fault, the contractor is not entitled to the contract price.
Outcome
Plaintiff's claim dismissed; defendant awarded costs
Facts
The defendant contracted the plaintiff to install aerial fibre optic cables and permanent poles for UGX 830,720,000. The defendant paid 50% down payment (UGX 415,360,000). The contract was to be completed by end of August 2013. In August 2013 the defendant suspended the works pending investigation and in October 2013 terminated the contract. The plaintiff claimed it had completed 81.56% of the works and sued for the outstanding balance of UGX 415,360,000, general damages, and interest. The defendant's evidence, including inspection reports, showed only 45% of the works were complete by October 2013. Communications between the parties showed the defendant was dissatisfied with the plaintiff's slow progress.
Issues
- Whether or not the plaintiff performed the contract to completion as agreed
- If not, what percentage of the contracted works was done by the plaintiff
- Whether there was a breach of contract, if any and by which party
- What remedies are available to the parties
Orders
- Suit dismissed.
- Costs to the defendant.
Rules and key headnotes
Legislation cited (4)
Cases cited (10)
- M'mairanyi & Others v Blue Shield Insurance Co Ltd (2005) 1 EA 280
- Pan African Insurance Company (U) Ltd v International Air Transport Association (HCCS No. 667 of 2003)
- Uganda Building Services v Yafesi Muzira t/a Quickest Builders & Co (HCCS No. 154 of 2005)
- Osman v Mulangwa (1995-1998) 2 EA 275 (SCU)
- Roko Construction Co v Attorney General (HCCS No. 517 of 2008)
- Registrar of Buildings v Bwogi (1986-1989) 1 EA 487
- Fire Masters Ltd v Huawei Technologies Co Ltd (HCT-00-CC-CS-119-2009)
- Hoeing v Isaacs [1952] All ER 176
- Cutter v Powell (1795) 101 ER 573
- Kagezi & Another v Ruparelia (2005) 2 EA 156
Cases citing this judgment (1)
How later Ugandan judgments in the Wakilii corpus have cited this case. Treatment labels come from Sequitur — Uganda’s citator — each backed by a verbatim span from the citing judgment, and are not an assertion that this case is, or is not, good law.
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.