Lydia Mugambe v Kayita James and Another (Civil Suit No. 339 of 2020)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that both defendants breached the construction agreement by failing to complete works within the stipulated time and by negligently performing finishing works that were defective, poorly supervised, and below professional standards. The defendants were jointly and severally liable for breach of contract and negligent performance. The 1st defendant signed the contract in his personal capacity as contractor and was thus personally liable alongside the 2nd defendant company. However, the claim of misrepresentation was not established as the plaintiff failed to prove the alleged representations were false or material to inducing the contract. Judgment for the plaintiff with damages awarded.
Outcome
Judgment entered for the plaintiff with damages and costs; counterclaim dismissed
Facts
The plaintiff entered into a construction agreement dated 3 July 2019 with the defendants for finishing works on a ten apartment block in Bweyogerere, Kiira. The works were to be completed within 6 months for UGX 450,000,000. The plaintiff paid UGX 320,000,000 by 12 November 2019. The defendants failed to complete the works within the agreed time. The plaintiff alleged the defendants performed shoddy work including cracked wall plaster, plaster peeling off walls, cracked ceiling plaster and cornices, defective and uneven door frames, and unlevelled or cracked floor tiles. The plaintiff alleged the defendants hired incompetent supervisors and workers. The defendants contended that the plaintiff breached the contract by failing to provide structural and architectural drawings, failing to provide supervising technical personnel, giving unreasonable instructions, and wrongfully dismissing workers from the site. The 2nd defendant filed a counterclaim for UGX 171,741,600 for unpaid balance and reimbursement of costs. The court visited the locus and observed the defects.
Issues
- Whether there was a breach of contract, and if so by whom?
- Whether the defendants negligently performed the construction works?
- Whether the 1st defendant misrepresented the 2nd defendant's technical capacity and capability to perform the contract?
- What remedies are available?
Orders
- Judgment entered for the plaintiff against the defendants jointly and severally.
- Special damages awarded to the plaintiff in the sum of UGX 27,000,000.
- General damages awarded to the plaintiff in the sum of UGX 225,000,000.
- Interest awarded on special damages at 15% per annum from the date of filing the suit.
- Interest awarded on general damages at 20% per annum from the date of judgment.
- Costs of the suit awarded to the plaintiff.
- Counterclaim dismissed.
Rules and key headnotes
Legislation cited (9)
- Contracts Act No. 07 of 2010 s.33(1)
- Contracts Act No. 07 of 2010 s.61(1)
- Companies Act 2012 s.20
- Building Control Act 2013 s.34
- Building Control Regulations 2020 Reg.5
- Building Control Regulations 2020 Reg.27
- Building Control Regulations 2020 Reg.29
- Building Control Regulations 2020 Reg.36
- Building Control Regulations 2020 Reg.42
Cases cited (11)
- Golden Construction Co. Ltd v Stateco (Nig) Ltd (2014) 8 NWLR (pt 1408)
- Henderson v Merrett Syndicates Ltd [1995] 2 AC 145
- Tesco Stores Ltd v Costain Construction Ltd & Others [2003] EWHC 1487 (TCC)
- Go Dante Yap v Bank Austria Creditanstalt AG [2011] 4 SLR 559
- Boschcon Civil & Electrical Construction Company (U) Ltd v Salini Costruttori Spa (Civil Suit No. 151 of 2008)
- Pasley v Freeman 3 TR 51, 100 ER 450 (KB)
- Hedley Byrne & Co Ltd v Heller & Partners Ltd [1963] 2 All ER 575
- Esso Petroleum Co Ltd v Mardon [1976] QB 801
- Esther Sempebwa v The Non-Performing Assets Recovery Trust (Civil Suit No. 0954 of 2004)
- The Kriti Palm [2007] All ER (Comm) 667
- Great Eastern Hotel Co Ltd v John Laing Construction Ltd & Anor [2005] EWHC 181
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.