Mamba Point Limited v Domus Aurea Limited (HCT-00-CC-CS-0638-2004) (HCT-00-CC-CS-0638-2004)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The court held that the defendant breached the contracts for supply of doors, windows, furniture and fittings by failing to meet agreed time frames, delivering defective materials, and failing to deliver remaining items. The defendant terminated the contract by written notice in February 2003. The plaintiff was awarded general damages of Shs.10,000,000 with interest at 22% per annum from judgment. The claim for special damages failed for lack of strict proof. The defendant's counterclaim for Shs.130,063,434 was dismissed for failure to prove indebtedness.
Outcome
Judgment entered for the plaintiff with general damages, interest and costs; counterclaim dismissed with costs to the plaintiff
Facts
The parties entered into contracts on 17 December 2001 for the defendant to supply doors, windows, door frames, window frames, furniture and fittings to the plaintiff. The plaintiff made advance payments totaling Shs.48,400,000. On 20 November 2002, the parties signed a Memorandum of Understanding setting out a scheme for completion with a total cost of Shs.77,369,461 and weekly time frames, with the balance to be assessed and paid within six months of completion. The defendant supplied all window and door frames, but the plaintiff discovered that the majority had warped. Performance was sluggish and behind schedule. The defendant failed to comply with the weekly review and payment mechanism set out in the Memorandum. An architect's report identified deviations from designs and specifications. On 21 February 2003, the plaintiff wrote pointing out breaches. The defendant responded on 4 March 2003 stating it could not and wished not to complete the work. The defendant submitted an updated proforma invoice increasing the total to Shs.152,532,850, which the plaintiff rejected. The defendant counterclaimed for Shs.130,063,434.
Issues
- Whether the defendant breached the contracts.
- Whether the contracts were terminated and by whom.
- Whether the parties are entitled to the reliefs claimed in the plaint and counterclaim.
Orders
- General damages awarded to the plaintiff in the sum of Shs.10,000,000.
- Interest on general damages at 22% per annum from the date of judgment until payment in full.
- Costs of the suit awarded to the plaintiff.
- Counterclaim dismissed.
- Costs of the counterclaim awarded to the plaintiff.
Rules and key headnotes
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.