Mbale Resort Hotel Ltd v Babcon Uganda Ltd (HCMA 265 of 2010)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The court partially set aside an arbitral award. The award of special damages of Shs.1,272,700,857 was set aside for lack of proof. The award of general damages of Shs.100,000,000 for punitive purposes was set aside as an error of law. The court held that an arbitral award should ordinarily be upheld unless shown to be bad on the face of it or to violate natural justice, but colossal sums claimed as special damages must be properly proved and general damages cannot be awarded for punitive purposes. The remainder of the award remained intact.
Outcome
Application partly allowed with two portions of the arbitral award set aside
Facts
Mbale Resort Hotel Ltd entered into a construction contract with Babcon Uganda Ltd on 14 June 2006 for construction of an annex building at Mbale Resort Hotel. The contract sum was Shs.666,337,984 with practical completion set for 30 October 2007. The applicant terminated the contract on 2 October 2007. The parties referred the dispute to arbitration before Hon. Justice A. Karokora (Rtd). On 8 April 2010, the arbitrator made an award requiring the applicant to pay Shs.1,712,880,153.34 comprising claims for design modifications (Shs.132,585,395.34), wrongful termination (Shs.1,272,700,857), various outstanding certificates and valuations (Shs.207,593,901), and general damages (Shs.100,000,000). The applicant applied to set aside the award on grounds that it did not accord with the Arbitration and Conciliation Act, was perverse with errors on its face, and reflected arbitrator misconduct.
Issues
- Whether the arbitral award was made in accordance with the Arbitration and Conciliation Act
- Whether the arbitrator applied the terms of the building contract when making the award
- Whether the arbitrator properly assessed special damages of Shs.1,272,700,857
- Whether the arbitrator was guilty of misconduct or exhibited partiality
- Whether the award of general damages for punitive purposes was proper
Orders
- Special damages of Shs.1,272,700,857 set aside
- General damages of Shs.100,000,000 set aside
- Remainder of arbitral award remains intact
- Applicant awarded one-third of its taxed bill of costs
Rules and key headnotes
Legislation cited (9)
- Arbitration and Conciliation Act s.34
- Arbitration and Conciliation Act s.34(2)(vii)
- Arbitration and Conciliation Act s.28(5)
- Arbitration and Conciliation Act s.28(1)
- Arbitration and Conciliation Act s.28(4)
- Arbitration and Conciliation Act s.19(1)
- Arbitration and Conciliation Act s.19(2)
- Arbitration and Conciliation Act s.26
- Arbitration and Conciliation Act Rule 13
Cases cited (6)
- Total Uganda Ltd v Buramba General Agencies [1997-2000] UCLR 412
- Contact Graphics Ltd v Vivilan Metal Products Ltd (Misc. Application 520 of 2006)
- Chevron Kenya Ltd & Anor v Dagare Transporters Ltd (Misc. Application 490 of 2008)
- Kilembe Mines Ltd v B M Steels Ltd (Misc. Application 002 of 2005)
- Associated Engineering Co. V Govt of Andara Pradesh [1991) 4 SCC 93 [AIR 1992 SC 233] Supreme Court
- Oil & Natural Gas Ltd. V Saw Pipes Ltd [2003) (5) SCC 705
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.