MH ConstructionCoLtd v Petro Uganda Ltd (High Court Civil Suit No. 425 of 2002)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that the plaintiff breached the construction contract by failing to complete agreed remedial works within ten days as stipulated in a settlement agreement dated 13 June 2002. The plaintiff's letter of 12 July 2002 requesting a seven-day extension constituted anticipatory breach entitling the defendant to terminate the contract. The defendant was not entitled to liquidated damages under clause 22 of the contract because it failed to produce the required architect's certification. The defendant was awarded UGX 5,000,000 as general damages for inconvenience caused by the breach.
Outcome
Plaintiff's suit dismissed; defendant awarded general damages of UGX 5,000,000 with interest and costs
Facts
On 19 November 2001, the plaintiff contracted to construct a petrol station for the defendant at Banda for UGX 217,231,829, with completion due by 20 January 2002. The plaintiff failed to complete by that deadline. By June 2002, work remained incomplete. On 13 June 2002, the parties signed a settlement agreement under which the plaintiff would complete outstanding works listed in a snag list within ten days, after which the defendant would pay UGX 35,840,796. On 29 June 2002, the defendant advanced UGX 6,392,000 by cheque to facilitate completion. The cheque cleared on 4 July 2002. On 12 July 2002, the plaintiff wrote requesting a further seven days to complete the works, citing traffic disturbance and rain. On 13 July 2002, the defendant terminated the contract and engaged others to complete the works.
Issues
- Whether the plaintiff breached the contract.
- Whether the defendant was entitled to terminate the contract.
- Whether there is merit in the defendant's counter-claim.
- What remedies are available.
Orders
- Plaintiff's suit dismissed with costs.
- Judgment entered in favour of the defendant on the counter-claim for UGX 5,000,000 as general damages.
- Plaintiff to pay interest on UGX 5,000,000 at court rate from 13 February 2005 until payment in full.
- Plaintiff to bear the costs of the counter-claim.
Rules and key headnotes
Legislation cited (2)
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.