Mohammed Saru v Jinja Central Division Council (High Court Civil Suit No. 223 of 2009)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that the defendant local government was liable to pay the plaintiff for work done and compensation costs arising from the contract's termination. The termination was mutually agreed through a memorandum of understanding after the defendant, acting on IGG recommendations, stopped the plaintiff from construction but directed it to maintain the site for 34 months. The defendant failed to follow contractual termination procedures under clause 25. Under quantum meruit, the plaintiff was entitled to compensation for maintaining the site as directed. The Attorney General was not liable as the IGG only made recommendations to the local government, which was obliged to implement them in accordance with law. Plaintiff awarded UGX 93,798,016 plus interest.
Outcome
Judgment entered for plaintiff for UGX 93,798,016 plus interest and costs. Third party claim dismissed.
Facts
The plaintiff was assigned a construction contract for the defendant's office block. After commencing and substantially performing the contract, the IGG investigated and found the work substandard, recommending that the contract be terminated and re-tendered. The defendant stopped the plaintiff from construction in June 2005 but directed it to guard and maintain the site. In November 2005, the defendant purported to terminate the contract, which the plaintiff contested as non-compliant with contractual provisions. The plaintiff remained on site until August 2008. The defendant commissioned the Ministry of Works and Transport to assess the plaintiff's work in April 2008. The parties then executed a memorandum of understanding terminating the contract and obliging the defendant to verify and pay the plaintiff's claims. The defendant failed to pay, leading to this suit.
Issues
- What is the quantum of damages that the plaintiff is entitled to?
- Who is liable to pay the plaintiff — the defendant or the third party (Attorney General)?
Orders
- The plaintiff is awarded Uganda shillings 10,377,516/= comprising unpaid work and interest on delayed payments up to April 2008.
- The plaintiff is awarded compensation of Uganda shillings 83,420,500/= for site maintenance and related costs.
- Interest is awarded on Uganda shillings 6,364,238/= at commercial bank lending rate of 25% per annum from May 2008 till payment.
- Interest is awarded on the compensation sum of Uganda shillings 83,420,500/= at 25% per annum from December 2008 to the date of judgment.
- Further interest on compensation costs at 21% per annum from the date of judgment till payment in full.
- The defendant shall pay the costs of the suit to the plaintiff and the third party.
- Third party claim against the Attorney General dismissed.
Rules and key headnotes
Legislation cited (14)
- Civil Procedure Act s.26
- Civil Procedure Act s.27
- Civil Procedure and Limitation (Miscellaneous Provisions) Act
- Inspectorate of Government Act 2002 s.8
- Inspectorate of Government Act 2002 s.9
- Inspectorate of Government Act 2002 s.10
- Inspectorate of Government Act 2002 s.14
- Inspectorate of Government Act 2002 s.21
- Local Governments Act Cap 243 s.6
- Constitution of Uganda art.226
- Constitution of Uganda art.230
- Constitution of Uganda art.231
- Evidence Act s.113
- Leadership Code Act
Cases cited (3)
- Gordon Sentiba and 2 Others v Inspectorate of Government (Civil Appeal No. 6 of 2008)
- Bank of Baroda Uganda Ltd v Wilson Buyondo Kamuganda (Supreme Court Civil Appeal No. 10 of 2004)
- Jivanji v Sanyo Electrical Co Ltd [2003] 1 EA
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.