Morex Contractors v Nakawa Division Local Government (HCT-00-CC-CS 34 of 2010)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that retention money is payable only upon completion of works and issue of completion certificate. Where contractor did not complete works, retention is not payable. However, employer's failure to pay certified interim certificate within 84 days constituted fundamental breach under the contract. Though contractor not entitled to retention, entitled to general damages for employer's fundamental breach. Plaintiff awarded Ushs 10,000,000 general damages with interest at 8% per annum from judgment date plus costs.
Outcome
Plaintiff awarded general damages of Ushs 10,000,000 with interest and costs for employer's fundamental breach, but claim for retention dismissed as works not completed
Facts
On 7 July 2006, plaintiff was awarded tender by second defendant for single surface dressing of Mutungo tank hill/church Road measuring 500 metres in first defendant's division, for contract sum of Ushs 147,593,050. Plaintiff commenced work on 14 December 2006. First defendant issued interim certificate No. 1 for Ushs 40,367,200 with retention of Ushs 4,036,720, and interim certificate No. 2 on 29 March 2007 for Ushs 35,787,000 with retention of Ushs 3,578,700. Certificate No. 1 was partially paid leaving balance of Ushs 2,049,039. Certificate No. 2 was paid late in November 2007, beyond the 84-day contractual period. Work came to standstill. Evidence showed plaintiff completed 51% of works. Eventually defendants hired new contractor to complete works. Plaintiff claimed unpaid balance, retention money and loss of future income.
Issues
- Whether the retention of Ushs 7,615,420/= is payable to the plaintiff.
- Whether there was breach of contract.
- What are the remedies available to the parties?
Orders
- Judgment on admission entered against defendants for Ushs 2,049,039/= being balance on certificate No. 1.
- Plaintiff's claim for retention sum of Ushs 7,615,420/= dismissed.
- Defendants found to have committed fundamental breach of contract by failing to pay interim certificate No. 2 within 84 days as required by contract.
- General damages of Ushs 10,000,000/= awarded to plaintiff.
- Interest at 8% per annum awarded from date of judgment until payment in full.
- Costs of the suit awarded to the plaintiff.
Rules and key headnotes
Cases cited (2)
- CHITTY ON CONTRACTS Vol. 2 at Paragraph 37-125
- Paragraph 37-130
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.