Municipal Board of Mombasa v Ogilvie (Civil Appeal No. 59 of 1955)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The Court of Appeal dismissed the appeal, holding that the injury for which special damages were claimed occurred no later than the date of completion of the contractor's work, and the claim was therefore barred by limitation. The court further held that even if a claim might lie for general damages arising from the architect's issue of final certificates, no such claim was made on the pleadings, and the expression 'further or other relief' was not wide enough to cover an award for general damages.
Outcome
Appeal dismissed; suit remains dismissed on grounds of limitation
Facts
The appellant Municipal Board employed a contractor, Hem Singh, to erect buildings at a cost of approximately £17,000 under two contracts dated March and July 1946. The respondent was engaged as architect with duties including preparation of plans, supervision, and issue of certificates. The buildings were completed in April 1947. After a six-month retention period, the respondent issued final certificates on 5 April 1948, and final payments of approximately £1,900 were made in May 1948. By 1950, grave defects of design, materials and workmanship caused the buildings to become dilapidated and dangerous. The appellant spent approximately £7,250 repairing the defects. The full extent of defects was not ascertained until February 1952, and repair work was not completed until September 1952. On 1 April 1954, the appellant sued both the contractor and the respondent for breach of contract and negligence, claiming the cost of remedying defects as special damages. The Supreme Court dismissed the suit on grounds of limitation. The appellant appealed only against the dismissal as to the respondent.
Issues
- Whether the suit was barred by limitation where final certificates were issued less than six years before action brought.
- Whether the issue of final certificates constituted a separate and severable breach of contract giving rise to a distinct cause of action.
- Whether a claim for general damages could be sustained under a prayer for 'further or other relief' where no specific claim for general damages was pleaded.
Orders
- Appeal dismissed.
- Costs awarded to the respondent.
- Costs arising from the filing of the notice of cross-appeal disallowed as it was filed unnecessarily.
Rules and key headnotes
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.