Network Civil Engineering Contractors Ltd and Paul Mwirumubi v Francis Mujjuni (Miscellaneous Application No. 3093 of 2023)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that where parties have agreed to an arbitration clause in their contract, the court must refer disputes arising from that contract to arbitration unless the arbitration agreement is null and void, inoperative or incapable of being performed. Claims arising under the Nyabuhuka-Mujunji Mini Hydro Power Point contract, including additional assignments executed as extensions of that contract, were referred to arbitration. Claims relating to the Lower Nsongya Mini Hydro Plant, which was not covered by the arbitration agreement, were retained by the court for adjudication.
Outcome
Claims under the Nyabuhuka-Mujunji contract referred to arbitration; claims under the Lower Nsongya project retained by the court for adjudication
Facts
The respondent sued the applicants in Civil Suit No. 0953 of 2022 for USD 22,500 as outstanding contractual sums arising from three transactions: consultancy services for the Nyabuhuka-Mujunji Mini Hydro Power Plant under a written contract dated 15 December 2014, additional work done after that contract on the same project, and consultancy services for the Lower Nsongya Mini Hydro Plant. The applicants sought to have the dispute referred to arbitration, relying on clause 9 of the Nyabuhuka-Mujunji contract which provided that any dispute arising from that contract which could not be amicably settled should be referred to arbitration. The respondent contended that only the Nyabuhuka-Mujunji contract contained an arbitration clause, while the other two claims arose from separate transactions with no signed agreements containing arbitration clauses.
Issues
- Whether the dispute arising from Civil Suit No. 0953 of 2022 should be referred to arbitration in accordance with the arbitration clause between the parties.
Orders
- Application partially allowed.
- All the respondent's claims under the Nyabuhuka-Mujunji Mini Hydro Power Point contract plus any further assignments thereunder are referred to arbitration.
- The court will adjudicate the claims in relation to the Lower Nsongya Mini Hydro Plant.
- Costs shall abide the main cause.
Rules and key headnotes
Legislation cited (4)
Cases cited (3)
- Orange Uganda Limited v Hits Telecom (U) Limited (Miscellaneous Application No. 0310 of 2013)
- Maisha Medical Supplies Ltd v Anhui Tiankang Medical Technology (Miscellaneous Application No. 657 of 2021)
- National Social Security Fund and Another v Alcon International Ltd (Civil Appeal No. 02 of 2008)
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.