Nsereko v Kasigwa (Civil Suit No. 881 of 2014)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Held that a valid construction contract existed between the parties personally, not with any company. The defendant breached the contract by failing to pay the third instalment when due and by failing to follow the dispute resolution procedure before terminating the contract. The plaintiff substantially performed the contract despite termination before the agreed completion date and was entitled to the outstanding balance and general damages.
Outcome
Judgment for plaintiff with damages and costs; defendant's counterclaim dismissed
Facts
On 31 March 2013, the plaintiff contracted with the defendant to construct a three-storey building at UGX 950,823,100. The contract provided for payment in instalments: 40% on commencement, 25% and 30% per variations, and 5% after six months of completion. The defendant paid the first two instalments. In December 2013, the plaintiff requested the third instalment (30%). The defendant did not pay but requested continued work. On 2 March 2014, the defendant terminated the contract and evicted the plaintiff before the agreed completion date, alleging poor workmanship. The plaintiff had obtained building materials on credit in anticipation of the third payment. By termination, approximately 80% of the work was completed. KCCA had halted construction from 23 April to 30 June 2013 pending approval of drawings.
Issues
- Whether there is a contract between the parties
- Whether any party breached the contract and which party breached the contract
- Whether the defendant can recover any reliefs from the counter claim
- What remedies are available to the parties
Orders
- Judgment entered for the plaintiff.
- Defendant to pay plaintiff UGX 155,493,578 being the balance outstanding from work done.
- Defendant to pay plaintiff UGX 50,000,000 being general damages.
- Sum in (1) to attract interest of 18% per annum from date of termination of contract till payment in full.
- Sum in (2) to attract interest of 15% per annum from date of judgment till payment in full.
- Defendant to pay costs of the suit.
Rules and key headnotes
Legislation cited (1)
Cases cited (3)
- Kasibante v Shell Uganda Ltd (HCCS No. 542 of 2006)
- Bolton v Mahadeva [1972] 1 WLR 1009
- Storms Bruks Aktie Bolay v John & Peter Hatarison [1905] AC 515
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.