Omega Construction Limited v Attorney General and Another (Miscellaneous Application 1613 of 2022)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
Application for temporary injunction restraining payment of a performance guarantee dismissed. Held that performance guarantees operate autonomously from underlying contracts and must be paid on complying demand unless fraud, illegality, or unconscionability is established. The applicant failed to demonstrate clear fraud or unconscionable conduct by the beneficiary in calling the guarantee. The autonomy principle prevents courts from interfering with payment obligations based on disputes in the underlying construction contract.
Outcome
Application dismissed with interim injunction set aside; bank not restrained from honouring performance guarantee
Facts
Omega Construction Limited contracted with the Ministry of Works and Transport to construct the Ssezibwa crossing for approximately UGX 12.2 billion. After substantial completion, the applicant raised payment certificates which the Ministry refused to pay, alleging the contractor failed to deploy key personnel, maintain valid securities, and complete certain works. The Ministry terminated the contract on 7 November 2022 and called on a performance guarantee of UGX 1,220,705,528 issued by Centenary Rural Development Bank. The applicant had previously terminated the contract on the same date citing non-payment of interim certificates and referred the dispute to adjudication. The applicant sought a temporary injunction restraining the bank from honouring the guarantee, arguing fraud and unconscionability.
Issues
- Whether the applicant has shown a prima facie case with a probability of success
- Whether the applicant will suffer irreparable injury which would not be adequately compensated by award of damages
- Where the balance of convenience lies between granting or refusing the temporary injunction
- Whether there is fraud or unconscionability in the 1st respondent's call on the performance guarantee
- Whether the 2nd respondent bank was on notice of fraud when the 1st respondent sought payment under the guarantee
Orders
- Application dismissed.
- Interim injunction order issued on 28th November 2022 set aside.
- 2nd respondent not restrained from honouring the demand made by the 1st respondent in respect of performance guarantee Ref. No. CRDB/MAPEERA PLATINUM/TF/21.01/05/2019.
- Costs of the application to abide the result of the suit.
Rules and key headnotes
Legislation cited (10)
- Constitution of the Republic of Uganda 1995 Article 28
- Constitution of the Republic of Uganda 1995 Article 126
- Judicature Act s.33
- Judicature Act s.38
- Civil Procedure Act s.98
- Arbitration and Conciliation Act s.6
- Civil Procedure Rules Order 41 rule 1
- Civil Procedure Rules Order 41 rule 2
- Civil Procedure Rules Order 41 rule 3
- Civil Procedure Rules Order 41 rule 9
Cases cited (20)
- E.A. Industries v Trufoods [1972] EA 420
- American Cyanamid Co v Ethicon Limited [1975] AC 396
- Geilla v Cassman Brown Co Ltd [1973] EA 358
- GAPCO Uganda Limited v Kaweesa and Another (Miscellaneous Application No. 259 of 2013)
- Fellowes and Son v Fisher [1976] 1 QB 122
- Leonardo SpA v Doha Bank Assurance Company LLC [2019] QIC (F) 6
- Alternative Power Solution Ltd v Central Electricity Board [2014] UKPC 3
- IE Contractors v Lloyd's Bank [1990] 2 Lloyd's Rep 496
- Sea-Cargo Skips v State Bank of India [2013] EWHC 177 (Comm)
- Edward Owen Engineering Ltd v Barclays Bank International Ltd [1978] 1 QB 159
- Intraworld Industries, Inc. v. Girard Trust Bank, 336 A.2d 316 (Pa. S.C. 1975)
- Sztejn v. J. Henry Schroder Banking Corp. - 177 Misc. 719, 31 N.Y.S.2d 631 (Sup. Ct. 1941)
- Enka Insaat Ve Sanayi v Banca Popolare Dell'Alto Adige [2009] EWHC 2410
- United Trading Corp v Allied Arab Bank [1985] 2 Lloyd's Rep 554
- Barclay Mowlem Construction Ltd v. Simon Engineering (Aust) Pty Ltd (1991) 23 NSWLR 451
- Wood Hall Ltd v. Pipeline Authority (1979) 141 CLR 443
- Derry v Peek [1889] 14 App Cas 337
- City Council of Kampala v Donozio Musisi Sekyaya (Civil Application No. 3 of 2000)
- Godfrey Sekitoleko and Four Others v Seezi Peter Mutabazi and Two Others [2001-2005] HCB 80
- Nsubuga and Another v Mutawe [1974] EA 487
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.