Wakilii

Orion Transformers and Electrics Limited v Uganda Electricity Distribution Company Limited [2025] UGPPDPAAT 32

Tribunal · 2025 Application Withdrawn (Approved) AI-generated summary ↓ Download Pin to watchlist Add to matter
Jurisdiction
Uganda
Case Type
Application for review of procurement decision, withdrawn by applicant with tribunal approval
Decision
Application withdrawn with tribunal approval; suspension order vacated

Observed later treatment

No later-treatment classification is recorded for this judgment.

Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.

AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.

Holding

The Tribunal approved the applicant's withdrawal of its procurement review application under regulation 16(3) of the PPDA Tribunal Procedure Regulations 2016. The respondent and best evaluated bidder did not object to the withdrawal. Each party was ordered to bear its own costs and the Tribunal's earlier suspension order was vacated.

Outcome

Application withdrawn with tribunal approval; suspension order vacated

Facts

Orion Transformers and Electrics Limited filed an application on 19 June 2025 challenging the outcome of a procurement process for the supply of distribution transformers under framework contract for Lots 1, 2 and 3 (Procurement No. UEDCL/SUPPLS/2023-24/10278) in respect of Lot 1. The respondent Uganda Electricity Distribution Company Limited and the best evaluated bidder Steema Transformers and Electricals Limited both filed responses on 23 June 2025. On 24 June 2025, the applicant's counsel filed a notice of withdrawal. At an oral hearing held via Zoom on 3 July 2025, the applicant reiterated its decision to withdraw and neither the respondent nor the best evaluated bidder objected.

Issues

  1. Whether the Tribunal should approve the applicant's withdrawal of the procurement review application.

Orders

  • The withdrawal of Registry Application No. 13 of 2025 by the Applicant is approved.
  • Each party shall bear its own costs.
  • The Tribunal's suspension order dated 19th June, 2025 is vacated.

Legislation cited (1)

  • Public Procurement and Disposal of Public Assets (Tribunal) (Procedure) Regulations, 2016 reg.16(3)

Full judgment

↓ Download PDF

The original judgment as reported. Read the original PDF before relying on any passage.

Orion Transformers and Electrics Limited v Uganda Electricity Distribution Company Limited 2025 UGPPDPAAT 32 (3 July 2025)
Source: this page presents Wakilii’s issue analysis and metadata for a publicly reported Ugandan judgment. Any AI-generated summary is marked as such. Judgment text is sourced from the Uganda Legal Information Institute (ulii.org). Wakilii is not affiliated with ULII.