Planbuild Technical Services Limited v Attorney General (Civil Suit No. 1273 of 2023)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The High Court held that a dispute concerning non-payment of retention monies under a construction contract fell within the scope of the arbitration clause where the dispute arose from a determination by the Project Manager. The court found that the Permanent Secretary's letter refusing payment constituted a Project Manager's decision under the contract, triggering the contractual dispute resolution mechanism. The suit was stayed and parties directed to arbitration in accordance with the contract's dispute settlement clause.
Outcome
Suit stayed and parties referred to arbitration
Facts
On 7 October 2010, the Plaintiff entered into a construction contract with the Government of Uganda through the Rural Electrification Agency for rural electrification schemes in Bushenyi and Rukungiri districts. The Plaintiff asserted it fully performed its contractual obligations and handed over completed works, but the Defendant failed to release retention monies of UGX 209,183,258 and did not issue a completion certificate. The Defendant contended the Plaintiff did not complete works according to specifications, failed to submit final accounts to the Project Manager before the end of the Defects Liability Period, and did not comply with requirements for project closure. The Permanent Secretary wrote to the Plaintiff on 9 November 2021 stating the money could not be paid as project closure had not been carried out.
Issues
- Whether the claim in this suit falls within the arbitration clause under the contract and is therefore governed by the Arbitration and Conciliation Act.
Orders
- The suit is stayed.
- The parties are directed to resolve the dispute by arbitration in accordance with the dispute settlement clause under the Agreement.
Rules and key headnotes
Legislation cited (4)
Cases cited (6)
- Babcon (U) Ltd v Mbale Resort Hotel (Civil Appeal No. 87 of 2011)
- Koboko District Local Government v Okujjo Swali (Miscellaneous Application No. 0001 of 2016)
- Fulgensius Mungereza v Africa Central (Civil Appeal No. 34 of 2001)
- Smile Communications Uganda Ltd v ATC Uganda Ltd & Anor (Arbitration Cause No. 4 of 2022)
- Heyam and Another v Darwins Ltd [1942] 1 All ER 337
- Insigma Technology Co Ltd v Alstom Technology Ltd [2009] SGCA 24
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.