Plinth Technical Works Ltd v Hoima Municipal Local Government Council (CAD ARB 63 of 2017)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The tribunal held that where parties mutually disengage from a construction contract and the dispute does not arise from a contested Project Manager decision, the dispute resolution clause provides for direct arbitration under GCC Clause 25.4 rather than the adjudication procedure under GCC Clause 24.1. The tribunal found that the parties had misinterpreted the dispute resolution clause by attempting to invoke adjudication when no Project Manager decision was in issue. The application for appointment of an arbitrator was granted.
Outcome
Application granted and arbitrator to be appointed to resolve dispute over outstanding payments
Facts
The parties executed a construction agreement on 13 December 2015 for road works in Hoima Municipality. Following mutual disengagement, a dispute arose regarding outstanding payments owed to the applicant contractor. On 11 August 2017, the applicant requested the Uganda Institute of Professional Engineers to appoint an adjudicator. UIPE appointed an adjudicator on 16 August 2017 under GCC Clause 24.1. The respondent initially did not respond but later confirmed acceptance of the adjudicator on 8 November 2017. By the date of filing the application to CADER, the appointed adjudicator had not presided over the dispute. The applicant applied to CADER for appointment of an arbitrator. Both parties agreed that no Project Manager decision was being contested and had not established a framework for adjudication proceedings.
Issues
- Whether the dispute arising from mutual disengagement falls within the adjudication procedure under GCC Clause 24.1 and 25.2-25.3, or within the general arbitration procedure under GCC Clause 25.4.
- Whether CADER has jurisdiction to appoint an arbitrator where no Project Manager decision is being contested.
Orders
- Application granted.
- Arbitrator to be appointed.
- Each party to bear its own costs.
Rules and key headnotes
Legislation cited (1)
- Arbitration Act
Cases cited (2)
- Phillips v Copping [1935] 1 KB 15
- Plinth Technical Works Ltd v Fort Portal Municipal Council (CAD ARB 62 of 2017)
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.