Polat Yol Yapi Sanvetic SA v Uganda National Roads Authourity (Miscellaneous Application 3 of 2022)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The court dismissed the application for an interim measure restraining termination of a road construction contract and enforcement of bank guarantees pending arbitration. While the applicant satisfied the threshold of demonstrating a serious question to be arbitrated, it failed to establish manifest fraud, unconscionable conduct, or that the beneficiary could not honestly believe in the validity of its demand. The balance of convenience favoured the respondent: demand guarantees embody an agreed allocation of risk, and restraining orders are rarely granted to prevent termination of construction contracts between sophisticated commercial parties.
Outcome
Application for interim measure of protection dismissed
Facts
On 7 November 2019, the respondent contracted the applicant to upgrade the Muyembe-Nakapiripirit Road. The contract commencement date was 30 March 2020. The respondent became dissatisfied with delayed commencement and on 18 January 2022 called on the advance payment guarantee (UGX 14,259,362,014 and USD 12,413,382) issued by DFCU Bank. On 25 January 2022 the respondent issued a termination notice. The applicant contended that COVID-19 pandemic disruptions in the supply chain caused the delay and that by 25 January 2022 all required equipment had been mobilised. The applicant sought to prevent enforcement of the guarantees pending arbitration. The respondent argued the dispute should be resolved through the contract's adjudication and arbitration clauses and that the contract had since been allowed to continue following ministerial intervention.
Issues
- Whether the applicant has a prima facie case or a serious question to be arbitrated with a probability of success.
- Whether the applicant will suffer irreparable harm if the restraining order does not issue.
- Whether the balance of convenience favours granting the restraining order.
- Whether the applicant established a strong prima facie case of fraud in the documents presented.
- Whether the respondent could not honestly have believed in the validity of its demand under the guarantee.
- Whether the guarantor knew of the fraud at the time the respondent sought payment under the guarantee.
Orders
- Application dismissed.
- Costs awarded to the respondent.
Rules and key headnotes
Legislation cited (2)
Cases cited (10)
- E.A. Industries v Trufoods [1972] E.A. 420
- American Cyanamid Co v Ethicon Limited [1975] AC 396
- Geilla v Cassman Brown Co Ltd [1973] E.A. 358
- GAPCO Uganda Limited v Kaweesa and another (Miscellaneous Application No. 259 of 2013)
- Edward Owen Engineering Ltd v Barclays Bank International Ltd [1978] 1 All ER 976
- Alternative Power Solution Ltd v Central Electricity Board [2014] UKPC 3
- Simon Carves Ltd v Ensus UK Ltd [2011] EWHC 657 (TCC)
- Doosan Babcock Ltd v Commercializadora de Equipos y Materiales Mabe Limitada [2013] EWHC 3010 (TCC)
- Barclay Mowlem Construction Ltd v Simon Engineering (Aust) Pty Ltd (1991) 23 NSWLR 451
- United Trading Corporation S.A. v Allied Arab Bank Ltd [1985] 2 Lloyd's Rep 554
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.