Prism Construction Company Limited v Attorney General (Miscellaneous Cause 76 of 2021)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The High Court dismissed the application for a mandatory injunction to restore the contractor to the construction site pending arbitration. The court held that the applicant failed to demonstrate that restoring possession was necessary to prevent harm to the arbitral process or preserve assets for a subsequent award. Damages were found to be an adequate remedy for the contractor's quantified claim. The balance of convenience favoured refusal where the eviction had already occurred and the parties' relationship required a high degree of cooperation which had broken down, making continued coexistence on site impracticable.
Outcome
Application for interim injunction dismissed; respondent (Ministry) permitted to proceed with completion of construction using alternative contractor
Facts
The applicant contractor entered a construction contract with the Ministry of Education dated 27 January 2020 to construct facilities at Uganda Technical College, Bushenyi. Disputes arose regarding slow progress and quality of materials. The contract period, after three extensions totalling nine months, expired on 1 August 2021. On or about 25 October 2021, the Ministry decided the contract had expired and would not be renewed. The Ministry called on the advance guarantee (UGX 1,480,182,257) and performance guarantee (UGX 981,966,874). The applicant commenced adjudication proceedings. On 28 October 2021, the Ministry evicted the applicant from the site. The applicant filed this application on or about late December 2021 seeking a mandatory injunction to restore it to possession of the site pending arbitration.
Issues
- Whether the applicant demonstrated a serious question to be arbitrated with sufficient likelihood of success to warrant a mandatory injunction restoring possession of the construction site.
- Whether the applicant faced an imminent risk of irreparable loss if not restored to the site pending arbitration.
- Whether the balance of convenience favoured granting a mandatory injunction restoring the applicant to the construction site.
Orders
- Application dismissed.
- Costs of the application awarded to the respondent.
Rules and key headnotes
Legislation cited (3)
- Arbitration and Conciliation Act s.6
- Civil Procedure Act s.98
- Civil Procedure Rules O.52 r.1
Cases cited (8)
- Kiyimba Kaggwa v Katende Haji Abdu Nasser [1985] HCB 44
- Leisure Data v Bell [1988] FSR 367
- Shepherd Homes Ltd v Sandham [1971] Ch 340
- Kiyimba Kagwa v Haji Abdu Nasser Katende [1985] HCB 43
- Mugenyi Yesero v Wandera Philemon K [1987] HCB 78
- Uganda Moslem Supreme Council v Kagimu Mulumba and Four Others [1980] HCB 110
- Films Rover International Ltd v Cannon Film Sales Ltd [1987] 1 WLR 670
- NWL Ltd v Woods [1979] 3 All ER 614
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.