R.R.P (U) Ltd v Assist (U) Ltd (Misc.Abitration Cause No. 4 of 2002)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The court set aside portions of an arbitral award on grounds of evident partiality. The arbitrator erred by importing the concept of force majeure where the contract referred only to extraordinary circumstances, allowing a claim of UGX 40,851,720 despite evidence of murram shortages and equipment idleness. Having found breach of contract by the respondent through supply of defective equipment, the arbitrator improperly denied general damages by suggesting the applicant should have walked away from the contract. The court set aside the award of UGX 40,851,720 and the denial of general damages, ordering security pending determination of damages.
Outcome
Portions of arbitral award set aside; enforcement of remaining awards stayed pending deposit of security or determination of damages claim
Facts
RRP (U) Ltd leased equipment from Assist (U) Ltd to perform a contract with the Ministry of Works. The equipment supplied by Assist was defective, broke down frequently, and performed below capacity. RRP disputed claims for payment when equipment was idle due to lack of murram and mechanical failures. RRP notified Assist of murram problems. The contract provided for notification of extraordinary circumstances and recording of hours when machines were idle. An arbitrator (Eng. Hans Mwesigwa) awarded Assist UGX 40,851,720 for the disputed period, finding payment was due whether or not murram was available as lack of murram did not constitute force majeure. The arbitrator also found both parties breached the contract but awarded no damages, reasoning that RRP should have walked away when equipment proved inadequate. RRP applied to set aside portions of the award.
Issues
- Whether the arbitrator demonstrated evident partiality in making the award.
- Whether the arbitrator erred in finding that payment for leased equipment was due for the entire period regardless of whether equipment was idle.
- Whether the arbitrator erred in refusing to award general damages after finding breach of contract by the respondent.
- Whether the arbitrator properly evaluated evidence relating to equipment breakdown and non-tasking.
Orders
- Award of UGX 40,851,720 set aside.
- Arbitrator's award A4 denying general damages for breach of contract set aside.
- Enforcement of awards of UGX 7,373,287 and UGX 121,543,610 and interest of 20% to abide determination of claim for general damages or deposit in court of UGX 128,916,897 as security.
- Respondent to deposit security of UGX 128,916,897 within 45 days.
- Costs of application awarded to applicant.
Rules and key headnotes
Legislation cited (8)
- Arbitration and Conciliation Act 7 of 2000 s.35
- Arbitration and Conciliation Act 7 of 2000 s.39
- Arbitration and Conciliation Act 7 of 2000 s.10
- Arbitration Rules r.13
- Arbitration Rules r.7
- Arbitration Rules r.8
- Judicature Statute s.35
- Constitution of Uganda 1995
Cases cited (2)
- Re Arbitration of Mulfibhai Madhvani v Lakham & Co Ltd (Misc Cause No. 4 of 1956)
- Total (U) Ltd v Burambe General Agencies (Arbitration Application No. 3 of 1998)
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.