Reenboog Construction Services Ltd v Aevar Engineering Services Ltd (Civil Suit No. 728 of 2019)
Observed later treatment
No later-treatment classification is recorded for this judgment.
Citator coverage is limited to judgments in the Wakilii corpus and source-matched treatment records. Absence of a signal is not an assertion that the case remains good law.
AI-generated summary. This summary was generated by AI from the full text of the judgment. It may contain errors or omissions—always read the source judgment before relying on it.
Holding
The court held that both parties breached the subcontract. The defendant breached by failing to pay UGX 168,417,325 for 96% of Phase 1 works completed and by removing the plaintiff's managing director as a co-signatory before full payment. The plaintiff breached by failing to complete works by the extended deadline of 6 June 2019. The defendant was ordered to pay the plaintiff UGX 167,967,000 plus interest at 6.5% per annum and general damages of UGX 1,000,000. The plaintiff was ordered to pay the defendant general damages of UGX 10,000,000 plus interest. Each party to bear its own costs.
Outcome
Judgment for plaintiff on main claim with damages awarded; counterclaim partly allowed with general damages awarded to defendant
Facts
On 12 March 2019, the plaintiff and defendant entered into a subcontract for construction of six classroom blocks in Yumbe for UGX 485,000,000. The subcontract originated from a main contract between UNICEF and the defendant. Payment was to be made in four phases, with Phase 1 payment of UGX 175,434,714 due upon completion of laying the ground slab. The plaintiff's managing director was made a co-signatory to the defendant's bank account to secure payment. The contract completion date was initially 15 May 2019, extended to 6 June 2019. UNICEF terminated the main contract on 13 July 2019. At termination, the plaintiff had completed 96% of Phase 1 works (ground slab work for two blocks complete, four blocks partially complete). The defendant did not pay the plaintiff for the work done and removed the plaintiff's managing director as a co-signatory. The plaintiff claimed UGX 167,967,000 for work done. The defendant counterclaimed for breach of contract, alleging the plaintiff failed to complete works by the agreed deadline.
Issues
- Whether the Defendant breached the subcontract by failing to pay for work done.
- Whether the Defendant breached the subcontract by removing the Plaintiff's managing director as a co-signatory to its bank account.
- Whether the Plaintiff breached the subcontract by failing to complete works by the agreed deadline.
- Whether either party is liable for unjust enrichment.
- What remedies are available to the parties?
Orders
- The Defendant breached the subcontract.
- The Plaintiff breached the subcontract.
- The Defendant is ordered to pay the Plaintiff UGX 167,967,000 as money owing for 96% of Phase 1 works done under the subcontract.
- Interest on the sum in the preceding order is granted at 6.5% per annum from the date of judgment until payment in full.
- General damages of UGX 1,000,000 are awarded to the Plaintiff.
- The Defendant is awarded general damages of UGX 10,000,000 for breach of the subcontract by the Plaintiff.
- Interest on the damages awarded to the Defendant is granted at 6.5% per annum from date when breach occurred until payment in full.
- Each party shall bear its own costs.
Rules and key headnotes
Legislation cited (2)
Cases cited (8)
- Ewadra Emmanuel v Spencon Services Limited (Civil Suit No. 022 of 2015)
- Madhupaper International Ltd & Another -v- Kenya Commercial Bank Ltd & Others [2003] 2 EA 562
- Harbutt's Plasticine Ltd -v- Wayne Tank and Pump Co Ltd [1970] 1 All ER 225
- Juma -v- Habibu [1975] 1 EA 108 (High Court of Tanzania)
- Interfreight Forwarders (U) Ltd -v- East Africa Development Bank
- Gullabhai Ushillingi v Kampala Pharmaceuticals Ltd (Supreme Court Civil Appeal No. 6 of 1999)
- Musoke v Departed Asians' Property Custodian Board & Anor (Supreme Court Civil Appeal No. 1 of 1992)
- Kampala City Council -v- Nakaye [1972] 1 EA 446
Full judgment
The original judgment as reported. Read the original PDF before relying on any passage.